2560-2564 S BENTLEY AVE 90064

Certificate Information: 2560-2564 S BENTLEY AVE 90064

Application / Permit
25014-10000-01154
Plan Check / Job No.
B25LA09973
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
[ePlan] NEW 1ST AND 2ND FLOOR ADDITION TO (E) SFD WITH ATTACHED (E) 1-CAR GARAGE TO HAVE ATTACHED ADU PER LAMC 12.22 A.33 (c) and (e). CONVERT A SECTION OF SFD TO JADU, WITH INT. AND EXT. STRUCTURAL REMODEL.
Permit Issued
Issued on 8/16/2025
Issuing Office
Current Status
CofO Issued on 2/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2025 APPLICANT
Assigned to Plan Check Engineer 3/27/2025 MAHNAZ NOURHASHEMI
Corrections Issued 4/3/2025 MAHNAZ NOURHASHEMI
Quality Review Completed 4/18/2025 HERNAN ARREOLA
Applicant returned to address corrections 6/12/2025 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 6/25/2025 MAHNAZ NOURHASHEMI
Plan Check Approved 7/15/2025 MAHNAZ NOURHASHEMI
Issued 8/16/2025 APPLICANT
CofO in Progress 2/12/2026 ARAM AVEDISIAN
Permit Finaled 2/17/2026 RICHARD STEINBACH
CofO Issued 2/17/2026 RICHARD STEINBACH
Permit Finaled 2/17/2026 RICHARD STEINBACH

Permit Application Clearance Information

GPI Written Notices Cleared 4/3/2025 MAHNAZ NOURHASHEMI
Specific Plan Cleared 4/7/2025 RICHARD WOO
Address approval Cleared 4/11/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/14/2025 RYAN CASTRO
Sewer availability Cleared 4/14/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 6/3/2025 RYAN CASTRO
Specific Plan Cleared 6/4/2025 KYLE WINSTON
Grading Pre-Inspection Cleared 7/11/2025 MAHNAZ NOURHASHEMI

Contact Information

Architect Ribeiro, De Moura, Ricardo Jorge; Lic. No.: C38075 5236 YARMOUTH AVE #113      ENCINO, CA 91316
Contractor Dragov Construction Group; Lic. No.: 1088785-B       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/19/2025 Not Ready for Inspection KIRK SANDERS
Underground Mechanical 8/19/2025 Partial Approval KIRK SANDERS
METHANE-Subgrade 8/25/2025 Corrections Issued MEL KHACHATOURIAN
Deputy Methane Barrier 8/26/2025 Conditional Approval MICHAEL PELHAM
METHANE-Subgrade 8/27/2025 Approved ASHLEY THOMPSON
Deputy Methane Barrier 9/10/2025 Conditional Approval KIRK SANDERS
BUILDING-Rough-Frame 9/16/2025 Corrections Issued KIRK SANDERS
Deputy Methane Barrier 9/16/2025 Approved KIRK SANDERS
Excavation/Setback/Form/Re-Bar 9/16/2025 Conditional Approval KIRK SANDERS
Footing/Foundation/Slab 9/16/2025 Conditional Approval KIRK SANDERS
METHANE-Barrier 9/16/2025 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/30/2025 Partial Approval MEL KHACHATOURIAN
Deputy Wood Construction 10/20/2025 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 10/21/2025 Approved MICHAEL ALLEN
HVAC-Rough 10/31/2025 Corrections Issued KIRK SANDERS
METHANE-Rough 10/31/2025 Not Ready for Inspection KIRK SANDERS
PLUMBING-Final 10/31/2025 Corrections Issued KIRK SANDERS
PLUMBING-Rough 10/31/2025 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 11/6/2025 Conditional Approval MICHAEL ALLEN
ELECTRICAL-Rough 11/6/2025 Approved MICHAEL ALLEN
Gas Test 11/6/2025 Approved MICHAEL ALLEN
Green Building Rough 11/6/2025 Not Ready for Inspection MICHAEL ALLEN
HVAC-Rough 11/6/2025 Approved MICHAEL ALLEN
MERV13>=Rough 11/6/2025 Approved MICHAEL ALLEN
METHANE-Final 11/6/2025 Not Ready for Inspection MICHAEL ALLEN
METHANE-Rough 11/6/2025 Approved MICHAEL ALLEN
PLUMBING-Rough 11/6/2025 Approved MICHAEL ALLEN
Shower Pan 11/6/2025 Approved MICHAEL ALLEN
Wood Frame 11/6/2025 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 11/12/2025 Approved MICHAEL ALLEN
Green Building Rough 11/12/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 11/12/2025 Partial Approval MICHAEL ALLEN
METHANE-Rough 11/12/2025 Approved MICHAEL ALLEN
Insulation 11/17/2025 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 11/17/2025 Approved KIRK SANDERS
Special/Order Compliance 11/17/2025 Corrections Issued KIRK SANDERS
Drywall Nailing 11/19/2025 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 11/25/2025 Approved KIRK SANDERS
Wood Frame 11/25/2025 Corrections Issued KIRK SANDERS
Rough-Elec/Plmb/HVAC 12/2/2025 Approved KIRK SANDERS
ELECTRICAL-Final 12/24/2025 Not Ready for Inspection KIRK SANDERS
Final 12/24/2025 Not Ready for Inspection KIRK SANDERS
Footing/Foundation/Slab 12/24/2025 Approved KIRK SANDERS
Green Building Final 12/24/2025 Not Ready for Inspection KIRK SANDERS
HVAC-Final 12/24/2025 Not Ready for Inspection KIRK SANDERS
MERV13>=Final 12/24/2025 Not Ready for Inspection KIRK SANDERS
PLUMBING-Final 12/24/2025 Not Ready for Inspection KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 12/24/2025 SGSOV Not Ready KIRK SANDERS
Service/Power Release 12/24/2025 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 12/24/2025 Not Ready for Inspection KIRK SANDERS
Underground Mechanical 1/15/2026 Approved KIRK SANDERS
Final 1/26/2026 Corrections Issued ARAM AVEDISIAN
Green Building Final 1/26/2026 Approved ARAM AVEDISIAN
MERV13>=Final 1/26/2026 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 1/26/2026 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 1/26/2026 Partial Approval ARAM AVEDISIAN
Final 2/9/2026 Partial Approval ARAM AVEDISIAN
Smoke Detectors 2/9/2026 Approved ARAM AVEDISIAN
ELECTRICAL-Final 2/12/2026 Approved ARAM AVEDISIAN
Final 2/12/2026 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 2/12/2026 Approved ARAM AVEDISIAN
PLUMBING-Final 2/12/2026 Approved ARAM AVEDISIAN