5741 W 18TH ST 90019
Certificate Information: 5741 W 18TH ST 90019
- Application / Permit
- 25014-10000-01144
- Plan Check / Job No.
- B25LA09882
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) TWO STORY ADDITION OF AN ADU TO AN (E) DETACHED GARAGE PER LAMC 12.22 A.33(b)(1).
- Permit Issued
- Issued on 1/23/2026
- Issuing Office
- Current Status
- Issued on 1/23/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2025 | SERGIO GUTIERREZ |
| Corrections Issued | 4/1/2025 | SERGIO GUTIERREZ |
| Quality Review Completed | 4/9/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 6/24/2025 | SERGIO GUTIERREZ |
| Plan Check Approved | 1/7/2026 | SERGIO GUTIERREZ |
| Issued | 1/23/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/14/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 4/14/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 4/26/2025 | RYAN CASTRO |
| Hydrant and Access approval | Cleared | 5/5/2025 | KENNETH FRASER |
| Construction near power lines | Cleared | 12/9/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/9/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Partner Construction Inc; Lic. No.: 1092170-B | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/13/2026 | Partial Inspection | BRENDAN MORELLI |
| Underground Mechanical | 3/13/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| PLUMBING-Rough | 3/16/2026 | Partial Approval | BRENDAN MORELLI |
| Sewer | 3/16/2026 | Approved | BRENDAN MORELLI |
| Underground Mechanical | 3/16/2026 | Partial Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 4/1/2026 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 4/7/2026 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2026 | Partial Approval | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2026 | Partial Approval | DAVID WILLIAMS |