3626 N CASTALIA AVE 90032
Certificate Information: 3626 N CASTALIA AVE 90032
- Application / Permit
- 25014-10000-01131
- Plan Check / Job No.
- B25LA09749
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT AND ADD TO (E) GARAGE TO CREATE A.D.U. PER STATE LAW (GCS 66323(a)(2))
- Permit Issued
- Issued on 5/19/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2025 | LAWRENCE QUIRANTE |
| Corrections Issued | 3/17/2025 | LAWRENCE QUIRANTE |
| Plan Check Approved | 5/14/2025 | SERGIO GUTIERREZ |
| Issued | 5/19/2025 | APPLICANT |
| CofO in Progress | 3/6/2026 | LILIANA PORTILLO |
| Permit Finaled | 3/7/2026 | DEROLD HAUFF |
| CofO Issued | 3/7/2026 | DEROLD HAUFF |
| Permit Finaled | 3/7/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/22/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 3/22/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/22/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/22/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2025 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 5/14/2025 | LAWRENCE QUIRANTE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21731 VENTURA BLVD SUITE 110 WOODLAND HILLS, CA 91364 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/17/2025 | Partial Approval | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 7/23/2025 | Approved | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 7/23/2025 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 7/23/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 9/8/2025 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2025 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 9/8/2025 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/12/2025 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 9/12/2025 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2025 | Partial Approval | LILIANA PORTILLO |
| Gas Test | 9/12/2025 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 9/12/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 9/12/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/8/2025 | Approved | DAVID WILLIAMS |
| Green Building Rough | 10/8/2025 | Approved | DAVID WILLIAMS |
| Insulation | 10/8/2025 | Approved | DAVID WILLIAMS |
| Drywall Nailing | 10/27/2025 | Corrections Issued | GEM DE OCAMPO |
| Drywall Nailing | 10/31/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 11/13/2025 | Approved | LILIANA PORTILLO |
| Shower Pan | 11/13/2025 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 1/28/2026 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 2/20/2026 | Approved | LILIANA PORTILLO |
| Final | 2/20/2026 | Conditional Approval | LILIANA PORTILLO |
| Green Building Final | 2/20/2026 | Approved | LILIANA PORTILLO |
| HVAC-Final | 2/20/2026 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 2/20/2026 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 2/20/2026 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 2/20/2026 | Approved | LILIANA PORTILLO |
| Final | 3/5/2026 | OK to Issue CofO | LILIANA PORTILLO |