2284 W 28TH ST 90018
Certificate Information: 2284 W 28TH ST 90018
- Application / Permit
- 25014-10000-01063
- Plan Check / Job No.
- B25LA09064
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL SINGLE-FAMILY DWELLING WITH REAR ADDITION
- Permit Issued
- Issued on 4/14/2025
- Issuing Office
- Current Status
- CofO Issued on 10/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2025 | ALEC MOUSAKHANIAN |
| Corrections Issued | 3/13/2025 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 3/25/2025 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 3/27/2025 | ALEC MOUSAKHANIAN |
| Issued | 4/14/2025 | APPLICANT |
| CofO in Progress | 10/21/2025 | MICHAEL LEWIS |
| Permit Finaled | 10/23/2025 | DEROLD HAUFF |
| CofO Issued | 10/23/2025 | DEROLD HAUFF |
| Permit Finaled | 10/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 3/19/2025 | DANIEL MATA |
| Roof/Waste drainage to street | Cleared | 3/26/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 3/26/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/27/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Advanced General Construction; Lic. No.: 951083-B | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/1/2025 | Conditional Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 5/5/2025 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 5/5/2025 | Partial Approval | MICHAEL LEWIS |
| Sewer | 5/9/2025 | Not Ready for Inspection | SABAS ALONSO |
| Underground Mechanical | 5/9/2025 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2025 | Corrections Issued | BARRY HACHE |
| Rough-Elec/Plmb/HVAC | 5/23/2025 | Corrections Issued | BARRY HACHE |
| BUILDING-Rough-Frame | 5/28/2025 | Conditional Approval | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 5/28/2025 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2025 | Approved | JOHN QUINTANILLA |
| METHANE-Rough | 5/28/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 5/28/2025 | Approved | JOHN QUINTANILLA |
| Deck | 5/30/2025 | Not Ready for Inspection | WAYNE REGESTER |
| ELECTRICAL-Rough | 5/30/2025 | Corrections Issued | WAYNE REGESTER |
| Footing/Foundation/Slab | 5/30/2025 | Approved | WAYNE REGESTER |
| Insulation | 5/30/2025 | Approved | WAYNE REGESTER |
| METHANE-Barrier | 5/30/2025 | Approved | WAYNE REGESTER |
| METHANE-Subgrade | 5/30/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 6/17/2025 | Approved | SABAS ALONSO |
| Drywall Nailing | 6/17/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 6/17/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 6/17/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 6/17/2025 | Partial Approval | SABAS ALONSO |
| Shower Pan | 7/1/2025 | Approved | RONNIE MEDINA |
| Final | 9/16/2025 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/16/2025 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 9/16/2025 | Approved | SABAS ALONSO |
| Final | 10/17/2025 | OK to Issue CofO | SABAS ALONSO |