4059 W GARDEN AVE 90039
Certificate Information: 4059 W GARDEN AVE 90039
- Application / Permit
- 25014-10000-01038
- Plan Check / Job No.
- B25LA08879
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. Addition to existing single family dwelling
- Permit Issued
- Issued on 3/31/2025
- Issuing Office
- Current Status
- CofO Issued on 11/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2025 | ADAM HEGAZI |
| Corrections Issued | 3/14/2025 | ADAM HEGAZI |
| Applicant returned to address corrections | 3/19/2025 | DANIEL SANJUAN |
| Plan Check Approved | 3/27/2025 | DANIEL SANJUAN |
| Issued | 3/31/2025 | APPLICANT |
| CofO in Progress | 11/5/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 11/9/2025 | DEROLD HAUFF |
| CofO Issued | 11/9/2025 | DEROLD HAUFF |
| Permit Finaled | 11/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/25/2025 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 3/25/2025 | LIAM ODONOVAN |
Contact Information
| Contractor | Ca Green Design Remodeling ; Lic. No.: 1025818-B | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/30/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 5/1/2025 | Approved | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 5/1/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Rough | 5/12/2025 | Partial Approval | NICHOLAS LOPEZ |
| Wood Frame | 5/12/2025 | Partial Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Partial Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2025 | Partial Approval | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 6/11/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 6/11/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 6/11/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| HVAC-Rough | 6/11/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Rough | 6/11/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 6/23/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 6/23/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 6/23/2025 | Approved | REGINA MENDEZ |
| Insulation | 6/25/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 6/25/2025 | Corrections Issued | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 7/1/2025 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 7/1/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 7/1/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 9/19/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 9/19/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 9/19/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| HVAC-Final | 9/19/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 9/19/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/19/2025 | SGSOV Approved | NICHOLAS LOPEZ |
| Smoke Detectors | 9/19/2025 | Approved | NICHOLAS LOPEZ |
| Final | 11/4/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 11/4/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 11/5/2025 | Approved | NICHOLAS LOPEZ |
| Final | 11/5/2025 | OK to Issue CofO | NICHOLAS LOPEZ |