1711 S HAYWORTH AVE 90035

Certificate Information: 1711 S HAYWORTH AVE 90035

Application / Permit
25014-10000-01035
Plan Check / Job No.
B25LA08868
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 6'-9" X 20'-11" 1-STORY ADDITION TO REAR OF (E) SFD. CONST. PER W.F.P.P. (1 OF 2)
Permit Issued
Issued on 5/22/2025
Issuing Office
Metro
Current Status
CofO Issued on 1/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/7/2025 APPLICANT
Assigned to Plan Check Engineer 3/10/2025 LAWRENCE QUIRANTE
Corrections Issued 3/12/2025 LAWRENCE QUIRANTE
Building Plans Picked Up 3/17/2025 APPLICANT
Applicant returned to address corrections 4/10/2025 CARLOS MONTES
Plan Check Approved 4/22/2025 CRISTINA SALAZAR
Issued 5/22/2025 APPLICANT
CofO in Progress 1/2/2026 BRENDAN MORELLI
Permit Finaled 1/2/2026 DEROLD HAUFF
CofO Issued 1/2/2026 DEROLD HAUFF
Permit Finaled 1/2/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/22/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/22/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/25/2025 LEE GUILBEAUX

Contact Information

Contractor Elite Construction And Cabinets Inc; Lic. No.: 1131283-B 1819 BELCROFT AVENUE      SOUTH EL MONTE, CA 91733
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/3/2025 Approved ARTHUR NEGRETE
METHANE-Barrier 6/3/2025 Approved ARTHUR NEGRETE
METHANE-Subgrade 6/3/2025 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 6/24/2025 Approved ARTHUR NEGRETE
Shower Pan 6/30/2025 Approved ANTHONY RAMOS
BUILDING-Rough-Frame 7/7/2025 Not Ready for Inspection ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 7/7/2025 Approved ARTHUR NEGRETE
Green Building Rough 7/7/2025 Not Ready for Inspection ARTHUR NEGRETE
METHANE-Rough 7/7/2025 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 7/15/2025 Corrections Issued ARTHUR NEGRETE
ELECTRICAL-Rough 7/17/2025 Approved ARTHUR NEGRETE
HVAC-Rough 7/17/2025 Not Ready for Inspection ARTHUR NEGRETE
Interior/Exterior Lathing 7/17/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 7/17/2025 Not Ready for Inspection ARTHUR NEGRETE
Deputy Wood Construction 7/18/2025 Conditional Approval ARTHUR NEGRETE
HVAC-Rough 7/30/2025 Corrections Issued ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 7/30/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 8/1/2025 Approved ARTHUR NEGRETE
Green Building Rough 8/1/2025 Approved ARTHUR NEGRETE
Insulation 8/1/2025 Approved ARTHUR NEGRETE
Drywall Nailing 8/11/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 10/29/2025 Corrections Issued WILLIAM SIERRA
Final 10/29/2025 Corrections Issued WILLIAM SIERRA
Green Building Final 10/29/2025 Not Ready for Inspection WILLIAM SIERRA
HVAC-Final 10/29/2025 Approved WILLIAM SIERRA
PLUMBING-Final 10/29/2025 Approved WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 10/29/2025 SGSOV Approved WILLIAM SIERRA
Service/Power Release 10/29/2025 Not Required WILLIAM SIERRA
Smoke Detectors 10/29/2025 Approved WILLIAM SIERRA
ELECTRICAL-Final 12/1/2025 No Access for Inspection BRENDAN MORELLI
Final 12/1/2025 No Access for Inspection BRENDAN MORELLI
Green Building Final 12/1/2025 No Access for Inspection BRENDAN MORELLI
HVAC-Final 12/1/2025 No Access for Inspection BRENDAN MORELLI
PLUMBING-Final 12/1/2025 No Access for Inspection BRENDAN MORELLI
Final 12/3/2025 Corrections Issued JUSTIN HAWLEY
Green Building Final 12/3/2025 Approved JUSTIN HAWLEY
Final 12/5/2025 Conditional Approval BRENDAN MORELLI
Final 12/12/2025 Conditional Approval BRENDAN MORELLI
Final 12/31/2025 OK to Issue CofO BRENDAN MORELLI