2325-2329 S SELBY AVE 90064
Certificate Information: 2325-2329 S SELBY AVE 90064
- Application / Permit
- 25014-10000-01034
- Plan Check / Job No.
- B25LA08852
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- *Eplan.*(N) addition of 2nd floor SB9 dwelling unit (per GSC 65852.21) and addition to connect (E) detahced ADU to main BLDG. Resulting in (N) Duplex with attached ADU (per LAMC 12.21 A.33 (c) and (e)).
- Permit Issued
- Issued on 12/7/2025
- Issuing Office
- Current Status
- Issued on 12/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2025 | ARSALAN SHABESTARI |
| Corrections Issued | 4/15/2025 | HUAN LE |
| Quality Review Completed | 4/29/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 7/21/2025 | ARSALAN SHABESTARI |
| Plan Check Approved | 11/19/2025 | ARSALAN SHABESTARI |
| Issued | 12/7/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/5/2025 | LANNY MERRICK |
| Address approval | Cleared | 5/9/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 5/9/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/16/2025 | LEE GUILBEAUX |
| Specific Plan | Cleared | 7/2/2025 | RICHARD WOO |
| Roof/Waste drainage to street | Cleared | 7/3/2025 | LIAM ODONOVAN |
| GPI Written Notices | Cleared | 10/30/2025 | HUAN LE |
| Senate Bill 9 | Cleared | 11/3/2025 | DANIEL CORONADO |
Contact Information
| Contractor | Sal Co Construction; Lic. No.: 779079-B | , |
| Engineer | Yaprak,, Taskin Tolga; Lic. No.: NA72927 | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/30/2026 | Conditional Approval | DAVID FEILER |
| Footing/Foundation/Slab | 2/23/2026 | Partial Approval | ARAM AVEDISIAN |
| METHANE-Barrier | 2/23/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| METHANE-Subgrade | 2/23/2026 | Approved | ARAM AVEDISIAN |
| Deputy Methane Barrier | 2/25/2026 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 3/2/2026 | Partial Approval | ARAM AVEDISIAN |
| METHANE-Barrier | 3/2/2026 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2026 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2026 | Partial Approval | RYAN SALAZAR |
| Deputy Wood Construction | 5/7/2026 | Conditional Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 5/12/2026 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 5/12/2026 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 5/12/2026 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 5/12/2026 | Not Ready for Inspection | ANTHONY EGSON |
| METHANE-Rough | 5/12/2026 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 5/12/2026 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 5/15/2026 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 5/15/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 5/15/2026 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2026 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 5/19/2026 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 5/19/2026 | Approved | KIRK SANDERS |
| METHANE-Rough | 5/19/2026 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/28/2026 | Corrections Issued | ARAM AVEDISIAN |
| Deputy Wood Construction | 5/28/2026 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 5/28/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| METHANE-Rough | 5/28/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| Shower Pan | 5/28/2026 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/2/2026 | Conditional Approval | ARAM AVEDISIAN |
| Green Building Rough | 6/2/2026 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 6/2/2026 | Partial Approval | ARAM AVEDISIAN |
| METHANE-Rough | 6/2/2026 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/5/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| Insulation | 6/5/2026 | Conditional Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 6/5/2026 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/11/2026 | Partial Inspection | WILBER ROSALES |
| Interior/Exterior Lathing | 6/11/2026 | Partial Inspection | WILBER ROSALES |
| Drywall Nailing | 6/22/2026 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 7/8/2026 | Conditional Approval | KIRK SANDERS |
| Drywall Nailing | 7/8/2026 | Approved | KIRK SANDERS |