2744 W LYTELLE PL 90065

Certificate Information: 2744 W LYTELLE PL 90065

Application / Permit
25014-10000-01013
Plan Check / Job No.
B25LA08660
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*Eplan.* (N) 2nd story ADU addition above (E) garage. ADU per LAMC 12.22 A.33(b)(1). <NFPA 13D fire sprinklers REQ Thru-out BLDG.>
Permit Issued
Issued on 8/21/2025
Issuing Office
Current Status
Issued on 8/21/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/7/2025 APPLICANT
Assigned to Plan Check Engineer 3/20/2025 KHEDER ALRAZAA
Corrections Issued 3/27/2025 HUAN LE
Quality Review Completed 4/29/2025 JOSE RODRIGUEZ
Applicant returned to address corrections 6/25/2025 HUAN LE
Plan Check Approved 8/12/2025 KHEDER ALRAZAA
Issued 8/21/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/21/2025 TAL SHEMEN
BHO/Hillside ordinance Cleared 5/21/2025 TAL SHEMEN
BHO/Hillside ordinance Cleared 5/21/2025 TAL SHEMEN
BHO/Hillside ordinance Cleared 5/21/2025 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 5/21/2025 TAL SHEMEN
Roof/Waste drainage to street Cleared 5/21/2025 TAL SHEMEN
Sewer availability Cleared 5/21/2025 TAL SHEMEN
Hydrant and Access approval Cleared 5/27/2025 FRANK GOMEZ
GPI Written Notices Cleared 6/25/2025 HUAN LE
Grading Pre-Inspection Cleared 6/25/2025 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/6/2025 Conditional Approval CHARLES BOGHOSKHAN
Footing/Foundation/Slab 10/7/2025 Corrections Issued RONNIE MEDINA
Pre-Inspection 10/7/2025 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 10/20/2025 Partial Approval RONNIE MEDINA
Footing/Foundation/Slab 10/24/2025 Approved DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Corrections Issued RONNIE MEDINA
BUILDING-Rough-Frame 2/4/2026 Corrections Issued RONNIE MEDINA
Floor/Roof Diaphrgm/Shear Wall 2/4/2026 Corrections Issued RONNIE MEDINA
MERV13>=Rough 2/4/2026 Approved RONNIE MEDINA
Rough-Elec/Plmb/HVAC 2/4/2026 Not Ready for Inspection RONNIE MEDINA
Verify Sprinkler Sign Off 2/4/2026 Not Ready for Inspection RONNIE MEDINA
BUILDING-Rough-Frame 2/18/2026 Corrections Issued RONNIE MEDINA
Floor/Roof Diaphrgm/Shear Wall 2/18/2026 Corrections Issued RONNIE MEDINA
Rough-Elec/Plmb/HVAC 2/18/2026 Not Ready for Inspection RONNIE MEDINA
Verify Sprinkler Sign Off 2/18/2026 Not Ready for Inspection RONNIE MEDINA
BUILDING-Rough-Frame 2/26/2026 Approved DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 2/26/2026 Approved DAVID WILLIAMS
Rough-Elec/Plmb/HVAC 2/26/2026 Approved DAVID WILLIAMS
Verify Sprinkler Sign Off 2/26/2026 Approved DAVID WILLIAMS
Insulation 3/10/2026 Approved GEM DE OCAMPO
Drywall Nailing 3/13/2026 Corrections Issued RONNIE MEDINA
Interior/Exterior Lathing 3/13/2026 Corrections Issued RONNIE MEDINA
Drywall Nailing 3/17/2026 Approved RONNIE MEDINA
Interior/Exterior Lathing 3/17/2026 Partial Approval RONNIE MEDINA
Shower Pan 3/17/2026 Approved RONNIE MEDINA