1405 N CORONADO ST 90026

Certificate Information: 1405 N CORONADO ST 90026

Application / Permit
25014-10000-00996
Plan Check / Job No.
B25LA08523
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO AN (E) SFD
Permit Issued
Issued on 4/22/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/5/2025 APPLICANT
Assigned to Plan Check Engineer 3/10/2025 FERNANDO FLORES
Corrections Issued 3/12/2025 FERNANDO FLORES
Building Plans Picked Up 3/14/2025 APPLICANT
Plan Check Approved 4/11/2025 NEHEMIAS RAMOS
Issued 4/22/2025 APPLICANT
CofO in Progress 3/4/2026 HAMIK HARTOUNIAN
Permit Finaled 3/4/2026 DEROLD HAUFF
CofO Issued 3/4/2026 DEROLD HAUFF
Permit Finaled 3/4/2026 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 3/15/2025 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 3/15/2025 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 3/15/2025 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 3/15/2025 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 3/15/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 3/15/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/15/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/17/2025 LEE GUILBEAUX
GPI Written Notices Cleared 4/11/2025 FERNANDO FLORES
Grading Pre-Inspection Cleared 4/11/2025 FERNANDO FLORES

Contact Information

Contractor Golden Estate Builders Inc; Lic. No.: 1113809-B 640 S CURSON AVE APT 305      LOS ANGELES, CA 90036
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/28/2025 Approved FREDDIE RIVERA
Footing/Foundation/Slab 4/28/2025 Approved FREDDIE RIVERA
Deputy Drilled-In Anchors 4/29/2025 Conditional Approval FREDDIE RIVERA
Wood Frame 5/2/2025 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 5/8/2025 Partial Approval HAMIK HARTOUNIAN
Insulation 5/8/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 5/8/2025 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/22/2025 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 6/23/2025 Corrections Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 6/23/2025 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 6/23/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/26/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 6/26/2025 Approved HAMIK HARTOUNIAN
HVAC-Rough 6/26/2025 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 6/26/2025 Partial Approval HAMIK HARTOUNIAN
Shower Pan 6/26/2025 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/1/2025 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 7/1/2025 Approved HAMIK HARTOUNIAN
Shower Pan 7/1/2025 Approved HAMIK HARTOUNIAN
Insulation 7/3/2025 Approved ALEX COLIN
Drywall Nailing 7/28/2025 Approved ALEX COLIN
ELECTRICAL-Final 11/7/2025 Approved HAMIK HARTOUNIAN
Final 11/7/2025 Partial Inspection HAMIK HARTOUNIAN
Green Building Final 11/7/2025 Approved HAMIK HARTOUNIAN
HVAC-Final 11/7/2025 Approved HAMIK HARTOUNIAN
PLUMBING-Final 11/7/2025 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 11/7/2025 SGSOV Approved HAMIK HARTOUNIAN
Service/Power Release 11/7/2025 Approved HAMIK HARTOUNIAN
Smoke Detectors 11/7/2025 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Final 11/13/2025 Corrections Issued HAMIK HARTOUNIAN
HVAC-Final 11/13/2025 Approved HAMIK HARTOUNIAN
PLUMBING-Final 11/13/2025 Approved HAMIK HARTOUNIAN
Special/Order Compliance 11/13/2025 Partial Inspection OSVALDO PARAMO
ELECTRICAL-Final 11/24/2025 Approved ALIZAH MAYAGOITIA
Final 2/13/2026 Partial Inspection HAMIK HARTOUNIAN
Smoke Detectors 2/13/2026 Approved HAMIK HARTOUNIAN
Final 2/27/2026 Partial Inspection HAMIK HARTOUNIAN
Final 3/4/2026 OK to Issue CofO HAMIK HARTOUNIAN