1433 W 67TH ST 90047
Certificate Information: 1433 W 67TH ST 90047
- Application / Permit
- 25014-10000-00987
- Plan Check / Job No.
- B25LA08460
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan convert (e) garage 203 sf to (n) adu + addition 190 sf total adu = 393 sf
- Permit Issued
- Issued on 5/16/2025
- Issuing Office
- Current Status
- Issued on 5/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2025 | JOSE VELAZQUEZ |
| Corrections Issued | 3/14/2025 | JOSE VELAZQUEZ |
| Plan Check Approved | 5/7/2025 | JOSE VELAZQUEZ |
| Issued | 5/16/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2025 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 3/17/2025 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2025 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 3/21/2025 | HISASHI KOBAYAKAWA |
| Construction near power lines | Cleared | 4/25/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hoerner,, John Brent; Lic. No.: S2145 | 24024 VIA CANDELA VALENCIA, CA 91355 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/3/2025 | Corrections Issued | BARRY HACHE |
| Sewer | 9/3/2025 | Not Ready for Inspection | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 9/5/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 9/5/2025 | Not Ready for Inspection | BARRY HACHE |
| Sewer | 9/5/2025 | Not Ready for Inspection | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 9/15/2025 | Partial Approval | BARRY HACHE |
| PLUMBING-Rough | 9/15/2025 | Partial Approval | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2025 | Corrections Issued | BARRY HACHE |
| Interior/Exterior Lathing | 12/9/2025 | Partial Approval | ALEX COLIN |
| Rough-Elec/Plmb/HVAC | 3/2/2026 | Corrections Issued | BARRY HACHE |
| BUILDING-Rough-Frame | 3/5/2026 | Partial Inspection | RAUL BARAJAS |
| Rough-Elec/Plmb/HVAC | 3/5/2026 | Corrections Issued | BARRY HACHE |
| Underground Mechanical | 3/5/2026 | Corrections Issued | BARRY HACHE |
| Rough-Elec/Plmb/HVAC | 3/18/2026 | Approved | BARRY HACHE |
| Underground Mechanical | 3/18/2026 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 3/31/2026 | Corrections Issued | BARRY HACHE |
| BUILDING-Rough-Frame | 4/17/2026 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2026 | Approved | ENRIQUE MIRELES |
| Insulation | 4/17/2026 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 4/22/2026 | Conditional Approval | ALEX COLIN |
| Shower Pan | 4/22/2026 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 5/5/2026 | Approved | ALEX COLIN |