12015 W HERBERT ST 90066

Certificate Information: 12015 W HERBERT ST 90066

Application / Permit
25014-10000-00982
Plan Check / Job No.
B25LA08420
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT WITH ADDITION PER GCS 66323(a)(2).
Permit Issued
Issued on 5/9/2025
Issuing Office
Current Status
Issued on 5/9/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/5/2025 APPLICANT
Assigned to Plan Check Engineer 3/11/2025 GIOVANNY CHAVEZ
Corrections Issued 3/12/2025 GIOVANNY CHAVEZ
Plan Check Approved 5/8/2025 SARKIS HARABEDIAN
Issued 5/9/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/13/2025 DARIN LAM
Roof/Waste drainage to street Cleared 3/13/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 3/14/2025 DARIN LAM
Sewer availability Cleared 3/14/2025 DARIN LAM
ZA Case Cleared 3/21/2025 DALIA MOKAYED
Specific Plan Cleared 4/29/2025 JOSHUA JONES
Construction near power lines Cleared 5/5/2025 RIDWAN HARDY

Contact Information

Contractor Maestro Construction Inc; Lic. No.: 1060987-B       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/26/2025 Approved RUBEN RIVAS
Sewer 11/12/2025 Partial Approval WILBER ROSALES
Underground Mechanical 11/12/2025 Approved WILBER ROSALES
Deputy Drilled-In Anchors 12/1/2025 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 12/4/2025 Approved WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 1/7/2026 Approved JESUS PINEDA
BUILDING-Rough-Frame 1/29/2026 Approved ANTHONY EGSON
ELECTRICAL-Rough 1/29/2026 Approved ANTHONY EGSON
Green Building Rough 1/29/2026 Approved ANTHONY EGSON
HVAC-Rough 1/29/2026 Approved ANTHONY EGSON
PLUMBING-Rough 1/29/2026 Approved ANTHONY EGSON
Insulation 2/3/2026 Corrections Issued DAKOTA LOW
Interior/Exterior Lathing 2/3/2026 Partial Approval DAKOTA LOW
Insulation 2/11/2026 Not Ready for Inspection ANTHONY EGSON
Drywall Nailing 2/17/2026 Approved DAKOTA LOW
Interior/Exterior Lathing 2/19/2026 Partial Approval DAKOTA LOW
Sewer 2/19/2026 No Access for Inspection DAKOTA LOW
Shower Pan 2/19/2026 Partial Approval DAKOTA LOW
Interior/Exterior Lathing 2/23/2026 Approved DAKOTA LOW
Sewer 2/23/2026 Approved DAKOTA LOW
Shower Pan 2/23/2026 Approved DAKOTA LOW
ELECTRICAL-Final 5/29/2026 Corrections Issued DAKOTA LOW
Final 5/29/2026 Corrections Issued DAKOTA LOW
Green Building Final 5/29/2026 Approved DAKOTA LOW
HVAC-Final 5/29/2026 Corrections Issued DAKOTA LOW
PLUMBING-Final 5/29/2026 Approved DAKOTA LOW
SGSOV-Seismic Gas S/O Valve 5/29/2026 SGSOV Approved DAKOTA LOW
Smoke Detectors 5/29/2026 Approved DAKOTA LOW
ELECTRICAL-Final 6/2/2026 No Access for Inspection DAKOTA LOW
Final 6/2/2026 No Access for Inspection DAKOTA LOW
HVAC-Final 6/2/2026 No Access for Inspection DAKOTA LOW
PLUMBING-Final 6/2/2026 No Access for Inspection DAKOTA LOW
ELECTRICAL-Final 6/5/2026 Approved MORRIS JACKSON
Final 6/5/2026 Corrections Issued MORRIS JACKSON
HVAC-Final 6/5/2026 Not Ready for Inspection MORRIS JACKSON
PLUMBING-Final 6/5/2026 Approved MORRIS JACKSON