10558 W WELLWORTH AVE 90024

Certificate Information: 10558 W WELLWORTH AVE 90024

Application / Permit
25014-10000-00959
Plan Check / Job No.
B25LA08118
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO EXISTING SINGLE FAMILY DWELLING
Permit Issued
Issued on 7/28/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2025 APPLICANT
Assigned to Plan Check Engineer 3/10/2025 CARLOS MONTES
Corrections Issued 3/11/2025 CARLOS MONTES
Building Plans Picked Up 3/12/2025 APPLICANT
Applicant returned to address corrections 6/2/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 7/21/2025 KELVIN CHUONG
Plan Check Approved 7/23/2025 SHANGQIN XIE
Issued 7/28/2025 APPLICANT
CofO in Progress 2/24/2026 MICHAEL ALLEN
Permit Finaled 2/26/2026 RICHARD STEINBACH
CofO Issued 2/26/2026 RICHARD STEINBACH
Permit Finaled 2/26/2026 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/12/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 5/14/2025 DAVID LOPEZ
ZA Case Cleared 5/29/2025 JASON CHAN
ZA Case Cleared 5/29/2025 JASON CHAN
Miscellaneous Cleared 7/18/2025 DIANA RENTERIA
Grading Pre-Inspection Cleared 5/29/2026 LANNY MERRICK

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/31/2025 Approved ARAM AVEDISIAN
Footing/Foundation/Slab 7/31/2025 Partial Approval ARAM AVEDISIAN
Rough-Elec/Plmb/HVAC 7/31/2025 Partial Approval ARAM AVEDISIAN
Shower Pan 7/31/2025 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 8/8/2025 Partial Approval STEPHANIE SWANSON
Interior/Exterior Lathing 8/8/2025 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 9/12/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 9/12/2025 Partial Approval MICHAEL ALLEN
Green Building Rough 9/12/2025 Not Ready for Inspection MICHAEL ALLEN
HVAC-Rough 9/12/2025 Approved MICHAEL ALLEN
PLUMBING-Rough 9/12/2025 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 9/18/2025 Partial Approval ARAM AVEDISIAN
Green Building Rough 9/18/2025 Not Ready for Inspection ARAM AVEDISIAN
Insulation 9/18/2025 Not Ready for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 10/2/2025 Approved ARAM AVEDISIAN
Green Building Rough 10/2/2025 Approved ARAM AVEDISIAN
Insulation 10/2/2025 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 10/2/2025 Partial Approval ARAM AVEDISIAN
Drywall Nailing 10/9/2025 Approved MICHAEL ALLEN
Final 1/8/2026 Corrections Issued MICHAEL ALLEN
Footing/Foundation/Slab 1/8/2026 Approved MICHAEL ALLEN
Green Building Final 1/8/2026 Conditional Approval MICHAEL ALLEN
METHANE-Barrier 1/8/2026 Approved MICHAEL ALLEN
METHANE-Final 1/8/2026 Approved MICHAEL ALLEN
METHANE-Subgrade 1/8/2026 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 1/8/2026 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 1/8/2026 Approved MICHAEL ALLEN
ELECTRICAL-Final 1/23/2026 Approved MICHAEL ALLEN
Final 1/23/2026 Corrections Issued MICHAEL ALLEN
Green Building Final 1/23/2026 Approved MICHAEL ALLEN
HVAC-Final 1/23/2026 Approved MICHAEL ALLEN
PLUMBING-Final 1/23/2026 Approved MICHAEL ALLEN
Final 2/23/2026 OK to Issue CofO MICHAEL ALLEN