2302 S CAMDEN AVE 90064

Certificate Information: 2302 S CAMDEN AVE 90064

Application / Permit
25014-10000-00914
Plan Check / Job No.
B25LA07742
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: PROPOSED 160 SQ.FT. INCLOSER OF EXISTING EXTERIOR PATIO ADD NEW SKYLIGHT. CREAT (N) CLOSET, (N) SWITCHES AND OUTLETS WHERE NEEDED, NEW EXTERIOR WOOD PANELING AND (N) CONCRETE SMOOTH SET TO MATCH EXISTING EXTERIOR -TYP.
Permit Issued
Issued on 6/25/2025
Issuing Office
Current Status
CofO Issued on 7/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2025 APPLICANT
Assigned to Plan Check Engineer 3/6/2025 RACHEL BEYENE
Corrections Issued 3/13/2025 RACHEL BEYENE
Quality Review Completed 3/26/2025 HERNAN ARREOLA
Applicant returned to address corrections 5/16/2025 RACHEL BEYENE
Plan Check Approved 6/24/2025 RAHEL BEYENE
Issued 6/25/2025 APPLICANT
CofO in Progress 7/20/2026 ARAM AVEDISIAN
Permit Finaled 7/20/2026 RICHARD STEINBACH
CofO Issued 7/20/2026 RICHARD STEINBACH
Permit Finaled 7/20/2026 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/4/2025 STEVEN JIN
Sewer availability Cleared 4/4/2025 STEVEN JIN
Eng Process Fee Ord 176,300 Cleared 4/14/2025 HISASHI KOBAYAKAWA

Contact Information

Architect Maloney,, John Leo; Lic. No.: C18424 3318 SHERBOURNE DR      CULVER CITY, CA 90232
Contractor Owner-Builder       ,
Engineer Grandhi,, Venkata Rohit; Lic. No.: C88709 7823 BOXWOOD CT      HIGHLAND, CA 92346

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/10/2026 Partial Inspection WILBER ROSALES
Wood Frame 4/10/2026 Not Ready for Inspection WILBER ROSALES
Pre-Inspection 4/20/2026 Partial Approval ANDREW NAVE
Wood Frame 4/20/2026 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 4/23/2026 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 4/29/2026 Approved RYAN SALAZAR
BUILDING-Rough-Frame 5/5/2026 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 5/5/2026 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 5/5/2026 Approved EUGENE CASSIDY
HVAC-Rough 5/5/2026 Not Ready for Inspection EUGENE CASSIDY
Interior/Exterior Lathing 5/7/2026 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 5/12/2026 Approved ANTHONY EGSON
HVAC-Rough 5/12/2026 Approved ANTHONY EGSON
Insulation 5/14/2026 Approved ANTHONY EGSON
Drywall Nailing 5/18/2026 Approved DAVID SCANTLIN
Final 6/26/2026 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 6/26/2026 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 6/26/2026 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 6/26/2026 Approved ARAM AVEDISIAN
Final 7/20/2026 OK to Issue CofO ARAM AVEDISIAN