3909-3909 1/2 W EXPOSITION BLVD 90016
Certificate Information: 3909-3909 1/2 W EXPOSITION BLVD 90016
- Application / Permit
- 25014-10000-00906
- Plan Check / Job No.
- B25LA07675
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERSION OF A STORAGE AND 2-CAR GARAGE INTO A SINGLE FAMILY DWELLING. RESULTING IN A SFD AT FIRST FLOOR, AND ADU AT FIRST & SECOND FLOOR.
- Permit Issued
- Issued on 8/20/2025
- Issuing Office
- Current Status
- CofO Issued on 3/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2025 | SERGIO GUTIERREZ |
| Corrections Issued | 3/11/2025 | SERGIO GUTIERREZ |
| Quality Review Completed | 3/20/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 7/15/2025 | SERGIO GUTIERREZ |
| Plan Check Approved | 8/20/2025 | SERGIO GUTIERREZ |
| Issued | 8/20/2025 | APPLICANT |
| CofO in Progress | 2/25/2026 | JUSTIN HAWLEY |
| No Progress | 2/26/2026 | DEROLD HAUFF |
| CofO in Progress | 2/26/2026 | DEROLD HAUFF |
| Permit Finaled | 3/17/2026 | DEROLD HAUFF |
| CofO Issued | 3/17/2026 | DEROLD HAUFF |
| Permit Finaled | 3/17/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/14/2025 | JEREMY CHOK |
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2025 | JEREMY CHOK |
| Sewer availability | Cleared | 4/14/2025 | JEREMY CHOK |
| Hydrant and Access approval | Cleared | 4/16/2025 | LAVEON RIDER |
| Metro Rail approval | Cleared | 4/23/2025 | JENNIFER SU |
| Flood clearance | Cleared | 4/25/2025 | SAMSON WONG |
| Highway dedication | Cleared | 6/24/2025 | CELINA MORENO |
Contact Information
| Architect | Winters,, Patrick Charles; Lic. No.: NA22032 | , |
| Contractor | Owner-Builder | , |
| Engineer | Varela,, Benjamin; Lic. No.: NA5714 | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/20/2025 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 12/16/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 12/16/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Insulation | 12/16/2025 | Approved | JUSTIN HAWLEY |
| Pre-Inspection | 12/16/2025 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 12/16/2025 | Approved | JUSTIN HAWLEY |
| Shower Pan | 12/16/2025 | Approved | JUSTIN HAWLEY |
| Special/Order Compliance | 12/16/2025 | Corrections Issued | JUSTIN HAWLEY |
| Drywall Nailing | 12/19/2025 | Approved | DEVON JACKSON |
| Interior/Exterior Lathing | 12/19/2025 | Approved | DEVON JACKSON |
| BUILDING-Rough-Frame | 2/25/2026 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 2/25/2026 | Approved | JUSTIN HAWLEY |
| Final | 2/25/2026 | OK to Issue CofO | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 2/25/2026 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 2/25/2026 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 2/25/2026 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 2/25/2026 | SGSOV Approved | JUSTIN HAWLEY |
| Smoke Detectors | 2/25/2026 | Approved | JUSTIN HAWLEY |