811-813 N VENDOME ST 90026

Certificate Information: 811-813 N VENDOME ST 90026

Application / Permit
25014-10000-00904
Plan Check / Job No.
B25LA07662
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Eplan: ADDITION TO REAR OF (E) DUPLEX TO EXPAND ONE UNIT. WORK PER ENGINEERED DESIGN.
Permit Issued
Issued on 6/19/2025
Issuing Office
Current Status
Issued on 6/19/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/28/2025 APPLICANT
Assigned to Plan Check Engineer 3/5/2025 OMAR GARNICA
Corrections Issued 3/6/2025 OMAR GARNICA
Applicant returned to address corrections 3/14/2025 OMAR GARNICA
Applicant returned to address corrections 5/29/2025 ALEC MOUSAKHANIAN
Plan Check Approved 6/18/2025 OMAR GARNICA
Issued 6/19/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/3/2025 CINDY QI
Eng Process Fee Ord 176,300 Cleared 4/3/2025 CINDY QI
Roof/Waste drainage to street Cleared 4/3/2025 CINDY QI
Sewer availability Cleared 4/3/2025 CINDY QI
"Q" conditions Cleared 4/22/2025 GEORGIA SMITH
GPI Written Notices Cleared 6/18/2025 OMAR GARNICA
Grading Pre-Inspection Cleared 6/18/2025 OMAR GARNICA

Contact Information

Contractor Owner-Builder       ,
Engineer Samadzadeh,, Hooman Ali; Lic. No.: C87661 22430 CRISWELL ST      WEST HILLS, CA 91307

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/24/2025 Corrections Issued FREDDIE RIVERA
Deputy Drilled-In Anchors 8/6/2025 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 8/12/2025 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 8/12/2025 Corrections Issued FREDDIE RIVERA
METHANE-Barrier 8/12/2025 Approved FREDDIE RIVERA
METHANE-Subgrade 8/12/2025 Approved FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 8/18/2025 Approved FREDDIE RIVERA
Deputy Drilled-In Anchors 10/1/2025 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 10/6/2025 Partial Approval FREDDIE RIVERA
Green Building Rough 10/6/2025 Partial Inspection FREDDIE RIVERA
METHANE-Rough 10/6/2025 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 11/4/2025 Partial Inspection FREDDIE RIVERA
Green Building Rough 11/4/2025 Partial Inspection FREDDIE RIVERA
METHANE-Rough 11/4/2025 Not Ready for Inspection FREDDIE RIVERA
Pre-Inspection 11/6/2025 Corrections Issued GEM DE OCAMPO
ELECTRICAL-Rough 11/7/2025 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 11/7/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Rough-Elec/Plmb/HVAC 11/17/2025 Approved FREDDIE RIVERA
Deputy Wood Construction 11/19/2025 Conditional Approval ALEX COLIN
BUILDING-Rough-Frame 11/20/2025 Approved BRENDAN MORELLI
Green Building Rough 11/20/2025 Approved BRENDAN MORELLI
Interior/Exterior Lathing 11/20/2025 Partial Approval BRENDAN MORELLI
METHANE-Rough 11/20/2025 Approved BRENDAN MORELLI
Insulation 11/26/2025 Approved FREDDIE RIVERA
Shower Pan 11/26/2025 Approved FREDDIE RIVERA
Drywall Nailing 12/10/2025 Approved GEM DE OCAMPO
ELECTRICAL-Final 3/11/2026 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Final 3/13/2026 Corrections Issued WILLIAM SIERRA
PLUMBING-Final 3/13/2026 Approved WILLIAM SIERRA
ELECTRICAL-Final 3/19/2026 Partial Inspection FREDDIE RIVERA
HVAC-Final 3/19/2026 Approved FREDDIE RIVERA
PLUMBING-Final 3/19/2026 Approved FREDDIE RIVERA
Smoke Detectors 3/19/2026 Approved FREDDIE RIVERA
ELECTRICAL-Final 3/31/2026 Approved FREDDIE RIVERA
Final 3/31/2026 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 3/31/2026 Approved FREDDIE RIVERA
Green Building Final 3/31/2026 Approved FREDDIE RIVERA
HVAC-Final 3/31/2026 Approved FREDDIE RIVERA
PLUMBING-Final 3/31/2026 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/31/2026 SGSOV Approved FREDDIE RIVERA
ELECTRICAL-Final 4/3/2026 Approved FREDDIE RIVERA
HVAC-Final 4/3/2026 Approved FREDDIE RIVERA
PLUMBING-Final 4/3/2026 Approved FREDDIE RIVERA
Service/Power Release 4/3/2026 Partial Inspection FREDDIE RIVERA
Special/Order Compliance 4/3/2026 Corrections Issued FREDDIE RIVERA
Final 4/8/2026 Partial Inspection FREDDIE RIVERA