8970 W 24TH ST 90034
Certificate Information: 8970 W 24TH ST 90034
- Application / Permit
- 25014-10000-00897
- Plan Check / Job No.
- B25LA07623
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan Remodel and Addition at rear of (E) 1-story SFD, all work per WFPP.
- Permit Issued
- Issued on 4/23/2025
- Issuing Office
- Current Status
- CofO in Progress on 6/3/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2025 | MINA HABILI |
| Corrections Issued | 3/11/2025 | MINA HABILI |
| Plan Check Approved | 4/8/2025 | MINA HABILI |
| Issued | 4/23/2025 | APPLICANT |
| CofO in Progress | 6/3/2026 | WILBER ROSALES |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/3/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2025 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/20/2026 | Conditional Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 2/24/2026 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 2/24/2026 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 3/4/2026 | Corrections Issued | WILBER ROSALES |
| Green Building Rough | 3/4/2026 | Not Ready for Inspection | WILBER ROSALES |
| PLUMBING-Rough | 3/4/2026 | Partial Approval | WILBER ROSALES |
| BUILDING-Rough-Frame | 3/9/2026 | Partial Approval | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2026 | Partial Approval | WILBER ROSALES |
| Insulation | 3/9/2026 | Partial Approval | WILBER ROSALES |
| ELECTRICAL-Rough | 3/25/2026 | Approved | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2026 | Partial Approval | WILBER ROSALES |
| HVAC-Rough | 3/25/2026 | Approved | WILBER ROSALES |
| PLUMBING-Rough | 3/25/2026 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 4/1/2026 | Approved | WILBER ROSALES |
| Green Building Rough | 4/1/2026 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 4/1/2026 | Approved | WILBER ROSALES |
| Insulation | 4/13/2026 | Approved | WILBER ROSALES |
| Drywall Nailing | 4/22/2026 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 4/22/2026 | Approved | WILBER ROSALES |
| Shower Pan | 4/22/2026 | Approved | WILBER ROSALES |
| ELECTRICAL-Final | 6/2/2026 | Approved | WILBER ROSALES |
| Final | 6/2/2026 | OK to Issue CofO | WILBER ROSALES |
| Green Building Final | 6/2/2026 | Approved | WILBER ROSALES |
| HVAC-Final | 6/2/2026 | Approved | WILBER ROSALES |
| PLUMBING-Final | 6/2/2026 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 6/2/2026 | SGSOV Approved | WILBER ROSALES |
| Smoke Detectors | 6/2/2026 | Approved | WILBER ROSALES |