2959 N FINCH ST 90039
Certificate Information: 2959 N FINCH ST 90039
- Application / Permit
- 25014-10000-00891
- Plan Check / Job No.
- B25LA07545
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel / Addition to (E) one story SFD. FIRE SPRINKLERS REQUIRED THROUGHOUT NFPA 13R.
- Permit Issued
- Issued on 8/1/2025
- Issuing Office
- Current Status
- CofO Issued on 4/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2025 | SERGIO GUTIERREZ |
| Corrections Issued | 3/11/2025 | SERGIO GUTIERREZ |
| Quality Review Completed | 3/14/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 5/16/2025 | SERGIO GUTIERREZ |
| Plan Check Approved | 7/18/2025 | SERGIO GUTIERREZ |
| Plan Check Approved | 7/23/2025 | SERGIO GUTIERREZ |
| Plan Check Approved | 8/1/2025 | SERGIO GUTIERREZ |
| Issued | 8/1/2025 | APPLICANT |
| CofO in Progress | 4/10/2026 | NICHOLAS LOPEZ |
| Permit Finaled | 4/12/2026 | DEROLD HAUFF |
| CofO Issued | 4/12/2026 | DEROLD HAUFF |
| Permit Finaled | 4/12/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2025 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 3/14/2025 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 3/14/2025 | ADRIAN SANCHEZ |
| Trees in Parkway | Cleared | 3/28/2025 | MIGUEL ORNELAS |
| ZI | Cleared | 4/3/2025 | DANIEL CORONADO |
| Hydrant and Access approval | Cleared | 4/17/2025 | RUEL COLE |
Contact Information
| Contractor | Castillo Construction Services Inc; Lic. No.: 1076756-B | 5617 LEXINGTON AVE APT 1 LOS ANGELES, CA 91106 |
| Engineer | Lobana,, Singh Maninder Pa; Lic. No.: C50989 | 885 PATRIOT DR #G MOORPARK, CA 93021 |
| Engineer | Shank,, Ken M; Lic. No.: L8271 | 2566 N FERNANDO RD LOS ANGELES, CA 90065 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/5/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2025 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 8/20/2025 | Partial Approval | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 8/21/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Green Building Rough | 8/21/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| MERV13>=Rough | 8/21/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Insulation | 8/22/2025 | Partial Approval | NICHOLAS LOPEZ |
| Wood Frame | 8/22/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Wood Frame | 8/26/2025 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 9/17/2025 | Approved | NICHOLAS LOPEZ |
| Wood Frame | 9/17/2025 | Partial Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2025 | Conditional Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 9/19/2025 | Approved | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 9/23/2025 | Corrections Issued | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 9/23/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 9/23/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| HVAC-Rough | 9/23/2025 | Approved | NICHOLAS LOPEZ |
| MERV13>=Rough | 9/23/2025 | Approved | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 9/29/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 9/29/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 9/29/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 9/29/2025 | Approved | NICHOLAS LOPEZ |
| Pre-Inspection | 12/10/2025 | Partial Approval | NICHOLAS LOPEZ |
| Insulation | 1/21/2026 | Conditional Approval | BRENDAN MORELLI |
| Drywall Nailing | 1/23/2026 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 2/6/2026 | Not Ready for Inspection | RONNIE MEDINA |
| Interior/Exterior Lathing | 2/9/2026 | Partial Approval | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 2/11/2026 | Approved | NICHOLAS LOPEZ |
| Service/Power Release | 3/12/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 3/19/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 3/19/2026 | Approved | NICHOLAS LOPEZ |
| Green Building Final | 3/19/2026 | Approved | NICHOLAS LOPEZ |
| MERV13>=Final | 3/19/2026 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/19/2026 | SGSOV Approved | NICHOLAS LOPEZ |
| Smoke Detectors | 3/19/2026 | Approved | NICHOLAS LOPEZ |
| Final | 3/31/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Pre-Inspection | 3/31/2026 | Partial Inspection | NICHOLAS LOPEZ |
| Final | 4/10/2026 | OK to Issue CofO | NICHOLAS LOPEZ |