517 S VAN NESS AVE 90020
Certificate Information: 517 S VAN NESS AVE 90020
- Application / Permit
- 25014-10000-00869
- Plan Check / Job No.
- B25LA07421
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. New Detached State ADU Per GCS 66323(a)(2). Work per WFPP.
- Permit Issued
- Issued on 3/12/2026
- Issuing Office
- Current Status
- Issued on 3/12/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2025 | EDWIN MARTINEZ |
| Corrections Issued | 3/10/2025 | EDWIN MARTINEZ |
| Applicant returned to address corrections | 1/21/2026 | EDWIN MARTINEZ |
| Applicant returned to address corrections | 1/29/2026 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 1/31/2026 | CRYSTEL MAALOUF |
| Plan Check Approved | 3/3/2026 | EDWIN MARTINEZ |
| Issued | 3/12/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/15/2025 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 3/15/2025 | EDGAR ALCARAZ |
| CPC | Cleared | 3/20/2025 | DAVID URITA |
| CPC | Cleared | 3/20/2025 | DAVID URITA |
| CPC | Cleared | 3/20/2025 | DAVID URITA |
| HPOZ | Cleared | 4/29/2025 | DAMIAN GATTO |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2026 | CELINA MORENO |
| Sewer availability | Cleared | 1/6/2026 | CELINA MORENO |
| Construction near power lines | Cleared | 2/28/2026 | NAOMI GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/17/2026 | Not Ready for Inspection | JOSH MEISTER |
| Underground Mechanical | 4/20/2026 | Approved | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 4/22/2026 | Corrections Issued | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 4/29/2026 | Corrections Issued | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 4/30/2026 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 4/30/2026 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 5/27/2026 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 5/27/2026 | Approved | JEFFREY MEAD |
| HVAC-Rough | 5/27/2026 | Not Ready for Inspection | JEFFREY MEAD |
| PLUMBING-Rough | 5/27/2026 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2026 | No Access for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 5/29/2026 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2026 | Approved | JEFFREY MEAD |
| Green Building Rough | 5/29/2026 | Approved | JEFFREY MEAD |
| HVAC-Rough | 5/29/2026 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 5/29/2026 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2026 | No Access for Inspection | JEFFREY MEAD |