Permit Issued
Issued on 5/12/2025
Issuing Office
Current Status
Issued on 5/12/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/25/2025 APPLICANT
Assigned to Plan Check Engineer 2/27/2025 STARR CHEN
Corrections Issued 3/1/2025 STARR CHEN
Quality Review Completed 3/3/2025 EUGENE BARBEAU
Plan Check Approved 5/12/2025 STARR CHEN
Issued 5/12/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/3/2025 DARIN LAM
Sewer availability Cleared 3/3/2025 DARIN LAM
Construction near power lines Cleared 4/9/2025 EDGAR PASCUA
Eng Process Fee Ord 176,300 Cleared 4/17/2025 DARIN LAM
GPI Written Notices Cleared 4/25/2025 STARR CHEN
Grading Pre-Inspection Cleared 4/25/2025 STARR CHEN

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/11/2025 Approved SEAN HAUPT
Pre-Inspection 8/18/2025 Approved CARLOS MATAMOROS
Deputy Drilled-In Anchors 8/29/2025 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 9/4/2025 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 9/19/2025 Partial Approval CARLOS MATAMOROS
Gas Test 9/19/2025 Approved CARLOS MATAMOROS
PLUMBING-Rough 9/19/2025 Partial Approval CARLOS MATAMOROS
Underground Mechanical 9/19/2025 Approved CARLOS MATAMOROS
Wood Frame 9/19/2025 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Approved CARLOS MATAMOROS
Special/Order Compliance 10/8/2025 Corrections Issued CARLOS MATAMOROS
Gas Test 10/20/2025 Approved CARLOS MATAMOROS
PLUMBING-Rough 10/20/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 11/25/2025 Approved CARLOS MATAMOROS
HVAC-Rough 11/25/2025 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 12/3/2025 Not Ready for Inspection DANIEL VERA
Green Building Rough 12/3/2025 Approved DANIEL VERA
Interior/Exterior Lathing 12/3/2025 Partial Approval DANIEL VERA
Insulation 12/9/2025 Partial Approval CARLOS MATAMOROS
Drywall Nailing 12/15/2025 Approved CHRISTOPHER WILSON
Shower Pan 1/15/2026 Approved EVAN COOPER
Shower Pan 1/22/2026 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 1/30/2026 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 2/5/2026 Approved EVAN COOPER
Underground Mechanical 4/15/2026 Partial Approval EVAN COOPER
Underground Mechanical 5/5/2026 Approved EVAN COOPER
ELECTRICAL-Final 5/13/2026 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 5/18/2026 Approved EVAN COOPER
HVAC-Final 5/18/2026 Approved EVAN COOPER
Service/Power Release 5/18/2026 Approved EVAN COOPER