9303 W KINCARDINE AVE 90034
Certificate Information: 9303 W KINCARDINE AVE 90034
- Application / Permit
- 25014-10000-00823
- Plan Check / Job No.
- B25LA07134
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan - 1ST FLOOR GARAGE ADDITION AND 2ND STORY ADU (484 SF) ADDITION PER 12.22 A33 C & D TO EXISITNG GARAGE
- Permit Issued
- Issued on 5/2/2025
- Issuing Office
- Current Status
- CofO Issued on 3/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2025 | STARR CHEN |
| Corrections Issued | 3/1/2025 | STARR CHEN |
| Quality Review Completed | 3/3/2025 | EUGENE BARBEAU |
| Plan Check Approved | 5/1/2025 | STARR CHEN |
| Issued | 5/2/2025 | APPLICANT |
| CofO in Progress | 3/13/2026 | ASHLEY THOMPSON |
| Permit Finaled | 3/13/2026 | RICHARD STEINBACH |
| CofO Issued | 3/13/2026 | RICHARD STEINBACH |
| Permit Finaled | 3/13/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 3/7/2025 | TAL SHEMEN |
| Miscellaneous | Cleared | 3/7/2025 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 3/7/2025 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2025 | TAL SHEMEN |
| Sewer availability | Cleared | 3/10/2025 | TAL SHEMEN |
| Hydrant and Access approval | Cleared | 3/13/2025 | JERRY KAO |
| Grading Pre-Inspection | Cleared | 3/14/2025 | VASIL MIHALEV |
| Specific Plan | Cleared | 4/23/2025 | NATHAN ROMINE |
| Construction near power lines | Cleared | 4/25/2025 | RIDWAN HARDY |
Contact Information
| Contractor | M D M Custom Remodeling Inc; Lic. No.: 930166-B | , |
| Contractor | Mdm General Contractor Room Additions; Lic. No.: 930166-B | , |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: NA88007 | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/30/2025 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 5/30/2025 | Partial Approval | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 6/2/2025 | Approved | EVAN COOPER |
| PLUMBING-Rough | 6/2/2025 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2025 | Corrections Issued | DANIEL VERA |
| Underground Mechanical | 6/13/2025 | Partial Approval | MEL KHACHATOURIAN |
| Underground Mechanical | 6/17/2025 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2025 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 6/30/2025 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 6/30/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| Rough-Elec/Plmb/HVAC | 6/30/2025 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 7/1/2025 | Conditional Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 7/15/2025 | Conditional Approval | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 7/15/2025 | Approved | ASHLEY THOMPSON |
| Shower Pan | 7/15/2025 | Approved | ASHLEY THOMPSON |
| Insulation | 7/30/2025 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 8/19/2025 | Approved | ASHLEY THOMPSON |
| Special/Order Compliance | 8/19/2025 | Partial Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 2/6/2026 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 2/6/2026 | Corrections Issued | ASHLEY THOMPSON |
| Final | 2/6/2026 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 2/6/2026 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 2/6/2026 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 2/6/2026 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 2/6/2026 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 2/6/2026 | SGSOV Not Ready | ASHLEY THOMPSON |
| Smoke Detectors | 2/6/2026 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 2/18/2026 | SGSOV Not Ready | ASHLEY THOMPSON |
| Final | 3/9/2026 | No Access for Inspection | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 3/9/2026 | SGSOV Not Ready | ASHLEY THOMPSON |
| Final | 3/11/2026 | OK to Issue CofO | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 3/11/2026 | SGSOV Approved | DANIEL VERA |