2945 S VICTORIA AVE 90016

Certificate Information: 2945 S VICTORIA AVE 90016

Application / Permit
25014-10000-00820
Plan Check / Job No.
B25LA07086
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND COVERT (E) DETACHED GARAGE TO ADU PER GC 66323(a)(2)
Permit Issued
Issued on 4/23/2025
Issuing Office
Current Status
CofO Issued on 1/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2025 APPLICANT
Assigned to Plan Check Engineer 2/28/2025 SERGIO MUNIZ
Corrections Issued 3/3/2025 SERGIO MUNIZ
Plan Check Approved 4/21/2025 SERGIO MUNIZ
Plan Check Approved 4/23/2025 INTERNET PERMIT
No Progress 4/23/2025 INTERNET PERMIT
Plan Check Approved 4/23/2025 INTERNET PERMIT
Plan Check Approved 4/23/2025 SERGIO MUNIZ
Issued 4/23/2025 APPLICANT
CofO in Progress 1/22/2026 JUSTIN HAWLEY
Permit Finaled 1/26/2026 DEROLD HAUFF
CofO Issued 1/26/2026 DEROLD HAUFF
Permit Finaled 1/26/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/3/2025 PAMELA TENEZA
Roof/Waste drainage to street Cleared 3/6/2025 CELINA MORENO
Construction near power lines Cleared 3/29/2025 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 4/8/2025 PAMELA TENEZA
Sewer availability Cleared 4/9/2025 CELINA MORENO

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor G Tech Smart Inc; Lic. No.: 1047801-B 16133 VENTURA BLVD SUITE 905      ENCINO, CA 91436
Contractor G Tech Smart Remodeling; Lic. No.: 1047801-B 16133 VENTURA BLVD SUITE 905      ENCINO, CA 91436

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/22/2025 Approved JUSTIN HAWLEY
Underground Mechanical 10/22/2025 Partial Approval JUSTIN HAWLEY
Deputy Drilled-In Anchors 10/23/2025 Conditional Approval JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 11/3/2025 Approved DEVON JACKSON
ELECTRICAL-Rough 11/6/2025 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 11/6/2025 Corrections Issued BRENDAN MORELLI
Sewer 11/6/2025 Not Ready for Inspection BRENDAN MORELLI
ELECTRICAL-Rough 11/7/2025 Approved WILLIAM SIERRA
HVAC-Rough 11/7/2025 Approved WILLIAM SIERRA
PLUMBING-Rough 11/7/2025 Approved WILLIAM SIERRA
Sewer 11/7/2025 Approved WILLIAM SIERRA
BUILDING-Rough-Frame 11/13/2025 Approved JUSTIN HAWLEY
Insulation 11/18/2025 Approved JUSTIN HAWLEY
Drywall Nailing 11/26/2025 Approved ALEX COLIN
Interior/Exterior Lathing 11/26/2025 Approved ALEX COLIN
Shower Pan 11/26/2025 Approved ALEX COLIN
BUILDING-Rough-Frame 1/20/2026 Approved JUSTIN HAWLEY
Final 1/20/2026 Corrections Issued JUSTIN HAWLEY
Green Building Final 1/20/2026 Approved JUSTIN HAWLEY
Green Building Rough 1/20/2026 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 1/20/2026 SGSOV Not Ready JUSTIN HAWLEY
Smoke Detectors 1/20/2026 Approved JUSTIN HAWLEY
Special/Order Compliance 1/20/2026 Corrections Issued JUSTIN HAWLEY
ELECTRICAL-Final 1/22/2026 Approved JUSTIN HAWLEY
Final 1/22/2026 OK to Issue CofO JUSTIN HAWLEY
HVAC-Final 1/22/2026 Approved JUSTIN HAWLEY
PLUMBING-Final 1/22/2026 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 1/22/2026 SGSOV Approved JUSTIN HAWLEY