344 N MCCADDEN PL 90004

Certificate Information: 344 N MCCADDEN PL 90004

Application / Permit
25014-10000-00800
Plan Check / Job No.
B25LA05994
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition and convert portion of (E) detached garage to ADU with garage per GCS 66323(a)(2)
Permit Issued
Issued on 5/11/2025
Issuing Office
Current Status
Issued on 5/11/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/18/2025 APPLICANT
Assigned to Plan Check Engineer 2/21/2025 AUNG SOE
Corrections Issued 2/25/2025 AUNG SOE
Applicant returned to address corrections 4/18/2025 AUNG SOE
Plan Check Approved 5/8/2025 SHANGQIN XIE
Issued 5/11/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/4/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 3/4/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 3/14/2025 JEANIE LAM
Sewer availability Cleared 3/14/2025 JEANIE LAM
CPC Cleared 4/15/2025 SUKI GERSHENHORN
HPOZ Cleared 4/15/2025 SUKI GERSHENHORN
Abandoned oil well Cleared 4/16/2025 LAVEON RIDER

Contact Information

Contractor R R Construction; Lic. No.: 608557-B       ,
Engineer Yamini,, Soly; Lic. No.: C33719 540 WARNER AVE      LOS ANGELES, CA 90024

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/23/2025 Conditional Approval RONNIE MINDANAO
Underground Mechanical 5/29/2025 Corrections Issued RONNIE MINDANAO
Underground Mechanical 6/2/2025 Approved ARTHUR NEGRETE
Footing/Foundation/Slab 6/12/2025 Not Ready for Inspection RONNIE MINDANAO
METHANE-Barrier 6/12/2025 Approved RONNIE MINDANAO
METHANE-Subgrade 6/12/2025 Approved RONNIE MINDANAO
Footing/Foundation/Slab 6/27/2025 Corrections Issued JOSE MACIAS
Deputy Drilled-In Anchors 6/30/2025 Conditional Approval REGINA MENDEZ
Footing/Foundation/Slab 7/3/2025 Corrections Issued RONNIE MINDANAO
PLUMBING-Rough 9/2/2025 Approved JEFFREY MEAD
Sewer 9/2/2025 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 9/3/2025 Approved RONNIE MINDANAO
Shower Pan 10/29/2025 Approved RONNIE MINDANAO
Underground Mechanical 10/29/2025 Approved RONNIE MINDANAO
HVAC-Rough 11/3/2025 Corrections Issued RONNIE MINDANAO
Interior/Exterior Lathing 11/4/2025 Approved RONNIE MINDANAO
ELECTRICAL-Rough 12/16/2025 Partial Approval RONNIE MINDANAO
HVAC-Rough 12/16/2025 Not Ready for Inspection RONNIE MINDANAO
Deputy Wood Construction 12/17/2025 Conditional Approval RONNIE MINDANAO
ELECTRICAL-Rough 12/18/2025 Conditional Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Approved RONNIE MINDANAO
HVAC-Rough 12/18/2025 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 12/22/2025 Conditional Approval RONNIE MINDANAO
ELECTRICAL-Final 12/22/2025 Not Ready for Inspection RONNIE MINDANAO
Final 12/22/2025 Not Ready for Inspection RONNIE MINDANAO
Footing/Foundation/Slab 12/22/2025 Approved RONNIE MINDANAO
Green Building Final 12/22/2025 Not Ready for Inspection RONNIE MINDANAO
Green Building Rough 12/22/2025 Not Ready for Inspection RONNIE MINDANAO
METHANE-Final 12/22/2025 Approved RONNIE MINDANAO
METHANE-Rough 12/22/2025 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 12/22/2025 SGSOV Not Ready RONNIE MINDANAO
Smoke Detectors 12/22/2025 Not Ready for Inspection RONNIE MINDANAO
ELECTRICAL-Rough 1/7/2026 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 1/7/2026 Approved RONNIE MINDANAO
HVAC-Rough 1/7/2026 Approved RONNIE MINDANAO
Insulation 1/22/2026 Conditional Approval RONNIE MINDANAO
Pre-Inspection 1/26/2026 Partial Inspection RONNIE MINDANAO
Underground Mechanical 2/5/2026 Corrections Issued RONNIE MINDANAO
Interior/Exterior Lathing 2/6/2026 Partial Approval JOSH MEISTER
Underground Mechanical 2/11/2026 Corrections Issued JEFFREY MEAD
Drywall Nailing 2/12/2026 Conditional Approval RONNIE MINDANAO
Underground Mechanical 2/13/2026 Not Ready for Inspection ENRIQUE MIRELES