2543 S VETERAN AVE 90064

Certificate Information: 2543 S VETERAN AVE 90064

Application / Permit
25014-10000-00778
Plan Check / Job No.
B25LA06661
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: PROPOSED ADDITION TO (E) SINGLE FAMILY DWELLING AND REMODEL.
Permit Issued
Issued on 4/10/2025
Issuing Office
Current Status
CofO Issued on 11/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/26/2025 APPLICANT
Assigned to Plan Check Engineer 2/28/2025 MIROOSH KHACHATOORIAN
Corrections Issued 3/1/2025 MIROOSH KHACHATOORIAN
Plan Check Approved 3/31/2025 SARKIS HARABEDIAN
Issued 4/10/2025 APPLICANT
CofO in Progress 11/12/2025 KIRK SANDERS
Permit Finaled 11/18/2025 RICHARD STEINBACH
CofO Issued 11/18/2025 RICHARD STEINBACH
Permit Finaled 11/18/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 3/3/2025 NATHAN ROMINE
Specific Plan Cleared 3/4/2025 RICHARD WOO
Grading Pre-Inspection Cleared 3/6/2025 VASIL MIHALEV
Roof/Waste drainage to street Cleared 3/7/2025 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 3/10/2025 TAL SHEMEN

Contact Information

Contractor Concept Renovations Inc; Lic. No.: 1016942-B       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/20/2025 Approved KIRK SANDERS
PLUMBING-Rough 6/2/2025 Partial Approval WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 6/10/2025 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 7/1/2025 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/1/2025 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 7/1/2025 Approved ARAM AVEDISIAN
PLUMBING-Rough 7/1/2025 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/8/2025 Approved MEL KHACHATOURIAN
PLUMBING-Rough 7/8/2025 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 8/6/2025 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 8/20/2025 Partial Approval KIRK SANDERS
Shower Pan 8/20/2025 Not Ready for Inspection KIRK SANDERS
Insulation 8/22/2025 Corrections Issued KIRK SANDERS
Shower Pan 8/22/2025 Corrections Issued KIRK SANDERS
Insulation 8/26/2025 Approved JAYLIN GRAVITTE
Shower Pan 8/26/2025 Approved JAYLIN GRAVITTE
Drywall Nailing 8/29/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 9/8/2025 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 10/30/2025 Not Ready for Inspection KIRK SANDERS
Final 10/30/2025 Not Ready for Inspection KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 10/30/2025 SGSOV Approved KIRK SANDERS
Smoke Detectors 10/30/2025 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 11/12/2025 Approved KIRK SANDERS
Final 11/12/2025 OK to Issue CofO KIRK SANDERS
Smoke Detectors 11/12/2025 Approved KIRK SANDERS