6917 1/2 N HESPERIA AVE 91335

Certificate Information: 6917 1/2 N HESPERIA AVE 91335

Application / Permit
25014-10000-00758
Plan Check / Job No.
B25LA06542
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Convert detached garage and addition to new 25' 10" x 36' 10" ADU per LAMC 12.22 A.33(b)(1)3. All work per engineer.
Permit Issued
Issued on 3/24/2025
Issuing Office
Current Status
CofO Issued on 12/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/20/2025 APPLICANT
Assigned to Plan Check Engineer 2/25/2025 NAREG ATARIAN
Corrections Issued 2/25/2025 NAREG ATARIAN
Plan Check Approved 3/19/2025 NAREG ATARIAN
Issued 3/24/2025 APPLICANT
CofO in Progress 12/15/2025 JUAN ALVARADO
Permit Finaled 12/17/2025 JOHN JANSON
CofO Issued 12/17/2025 JOHN JANSON
Permit Finaled 12/17/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/26/2025 WALLIE JONG
Roof/Waste drainage to street Cleared 2/26/2025 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 2/27/2025 WALLIE JONG
Sewer availability Cleared 2/27/2025 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/19/2025 Not Ready for Inspection JUAN ALVARADO
Underground Mechanical 5/19/2025 Partial Approval JUAN ALVARADO
Excavation/Setback/Form/Re-Bar 5/28/2025 Corrections Issued JUAN ALVARADO
Excavation/Setback/Form/Re-Bar 6/3/2025 Approved JUAN ALVARADO
Underground Mechanical 6/3/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 7/25/2025 Corrections Issued ROBERT GOLD
ELECTRICAL-Rough 7/25/2025 Approved ROBERT GOLD
Green Building Rough 7/25/2025 Not Ready for Inspection ROBERT GOLD
HVAC-Rough 7/25/2025 Approved ROBERT GOLD
PLUMBING-Rough 7/25/2025 Approved ROBERT GOLD
BUILDING-Rough-Frame 8/4/2025 Conditional Approval JUAN ALVARADO
Green Building Rough 8/4/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 8/4/2025 Approved JUAN ALVARADO
Insulation 8/11/2025 Approved JUAN ALVARADO
Drywall Nailing 8/18/2025 Approved JUAN ALVARADO
Shower Pan 8/18/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 8/26/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 8/27/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 10/21/2025 Approved JUAN ALVARADO
Final 10/21/2025 Corrections Issued JUAN ALVARADO
Footing/Foundation/Slab 10/21/2025 Approved JUAN ALVARADO
Green Building Final 10/21/2025 Approved JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 10/21/2025 SGSOV Not Ready JUAN ALVARADO
Smoke Detectors 10/21/2025 Approved JUAN ALVARADO
Final 11/4/2025 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 11/4/2025 SGSOV Approved ARUTYUN MADATYAN
Final 12/4/2025 Corrections Issued JUAN ALVARADO
ELECTRICAL-Final 12/12/2025 Approved JUAN ALVARADO
Final 12/12/2025 OK to Issue CofO JUAN ALVARADO
HVAC-Final 12/12/2025 Approved JUAN ALVARADO
PLUMBING-Final 12/12/2025 Approved JUAN ALVARADO
Service/Power Release 12/12/2025 Approved JUAN ALVARADO