8002 S CROYDON AVE 90045

Certificate Information: 8002 S CROYDON AVE 90045

Application / Permit
25014-10000-00731
Plan Check / Job No.
B25LA06268
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. CONVERSION OF [E] GARAGE AND ADDITION INTO A STATE ADU ( 508 SQ.FT) PER GCS 66323(a)(1). CONST. PER W.F.P.P.
Permit Issued
Issued on 9/17/2025
Issuing Office
Current Status
CofO Issued on 3/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2025 APPLICANT
Assigned to Plan Check Engineer 2/24/2025 EDWIN MARTINEZ
Corrections Issued 2/25/2025 EDWIN MARTINEZ
Applicant returned to address corrections 3/20/2025 LAWRENCE QUIRANTE
Applicant returned to address corrections 4/1/2025 LAWRENCE QUIRANTE
Plan Check Approved 4/5/2025 LAWRENCE QUIRANTE
Issued 9/17/2025 APPLICANT
CofO in Progress 2/27/2026 JESUS PINEDA
Permit Finaled 3/5/2026 RICHARD STEINBACH
CofO Issued 3/5/2026 RICHARD STEINBACH
Permit Finaled 3/5/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 2/26/2025 DARIN LAM
Roof/Waste drainage to street Cleared 2/26/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 2/27/2025 DARIN LAM
Sewer availability Cleared 2/27/2025 DARIN LAM
Construction near power lines Cleared 3/5/2025 RIDWAN HARDY
Construction within easement Cleared 3/5/2025 RIDWAN HARDY
Specific Plan Cleared 3/11/2025 PEDRO AYALA

Contact Information

Contractor Strong Builders Choice Inc; Lic. No.: 1136279-B       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 9/30/2025 Corrections Issued JESUS PINEDA
PLUMBING-Rough 9/30/2025 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 10/3/2025 Approved JESUS PINEDA
Pre-Inspection 10/17/2025 Partial Inspection JESUS PINEDA
ELECTRICAL-Rough 11/5/2025 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 11/5/2025 Corrections Issued TEMISTOCLES CAAL
HVAC-Rough 11/5/2025 Corrections Issued BOBBY KEY
Special/Order Compliance 11/5/2025 Partial Inspection HERBERT GIRON
ELECTRICAL-Rough 11/7/2025 Not Ready for Inspection JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Approved JESUS PINEDA
HVAC-Rough 11/7/2025 Approved JESUS PINEDA
PLUMBING-Rough 11/7/2025 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 11/12/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 11/12/2025 Not Ready for Inspection JESUS PINEDA
Green Building Rough 11/12/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 11/12/2025 Partial Approval JESUS PINEDA
PLUMBING-Rough 11/12/2025 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 11/19/2025 Approved JESUS PINEDA
ELECTRICAL-Rough 11/19/2025 Approved JESUS PINEDA
Insulation 11/19/2025 Corrections Issued JESUS PINEDA
PLUMBING-Rough 11/19/2025 Approved JESUS PINEDA
Drywall Nailing 11/25/2025 Approved JESUS PINEDA
Insulation 11/25/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 12/15/2025 Corrections Issued JESUS PINEDA
Sewer 12/15/2025 Corrections Issued JESUS PINEDA
Shower Pan 12/15/2025 Corrections Issued JESUS PINEDA
Underground Mechanical 12/15/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 12/17/2025 Approved JESUS PINEDA
Sewer 12/17/2025 Approved JESUS PINEDA
Shower Pan 12/17/2025 Approved JESUS PINEDA
Final 1/22/2026 Corrections Issued JESUS PINEDA
Green Building Final 1/22/2026 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 1/22/2026 SGSOV Approved JESUS PINEDA
Smoke Detectors 1/22/2026 Approved JESUS PINEDA
Final 1/28/2026 Corrections Issued JESUS PINEDA
Final 2/3/2026 Not Ready for Inspection JESUS PINEDA
Final 2/26/2026 OK to Issue CofO JESUS PINEDA