8002 S CROYDON AVE 90045
Certificate Information: 8002 S CROYDON AVE 90045
- Application / Permit
- 25014-10000-00731
- Plan Check / Job No.
- B25LA06268
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. CONVERSION OF [E] GARAGE AND ADDITION INTO A STATE ADU ( 508 SQ.FT) PER GCS 66323(a)(1). CONST. PER W.F.P.P.
- Permit Issued
- Issued on 9/17/2025
- Issuing Office
- Current Status
- CofO Issued on 3/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2025 | EDWIN MARTINEZ |
| Corrections Issued | 2/25/2025 | EDWIN MARTINEZ |
| Applicant returned to address corrections | 3/20/2025 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 4/1/2025 | LAWRENCE QUIRANTE |
| Plan Check Approved | 4/5/2025 | LAWRENCE QUIRANTE |
| Issued | 9/17/2025 | APPLICANT |
| CofO in Progress | 2/27/2026 | JESUS PINEDA |
| Permit Finaled | 3/5/2026 | RICHARD STEINBACH |
| CofO Issued | 3/5/2026 | RICHARD STEINBACH |
| Permit Finaled | 3/5/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 2/26/2025 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 2/26/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2025 | DARIN LAM |
| Sewer availability | Cleared | 2/27/2025 | DARIN LAM |
| Construction near power lines | Cleared | 3/5/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/5/2025 | RIDWAN HARDY |
| Specific Plan | Cleared | 3/11/2025 | PEDRO AYALA |
Contact Information
| Contractor | Strong Builders Choice Inc; Lic. No.: 1136279-B | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 9/30/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 9/30/2025 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 10/3/2025 | Approved | JESUS PINEDA |
| Pre-Inspection | 10/17/2025 | Partial Inspection | JESUS PINEDA |
| ELECTRICAL-Rough | 11/5/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2025 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Rough | 11/5/2025 | Corrections Issued | BOBBY KEY |
| Special/Order Compliance | 11/5/2025 | Partial Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 11/7/2025 | Not Ready for Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2025 | Approved | JESUS PINEDA |
| HVAC-Rough | 11/7/2025 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 11/7/2025 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 11/12/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 11/12/2025 | Not Ready for Inspection | JESUS PINEDA |
| Green Building Rough | 11/12/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 11/12/2025 | Partial Approval | JESUS PINEDA |
| PLUMBING-Rough | 11/12/2025 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 11/19/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 11/19/2025 | Approved | JESUS PINEDA |
| Insulation | 11/19/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 11/19/2025 | Approved | JESUS PINEDA |
| Drywall Nailing | 11/25/2025 | Approved | JESUS PINEDA |
| Insulation | 11/25/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 12/15/2025 | Corrections Issued | JESUS PINEDA |
| Sewer | 12/15/2025 | Corrections Issued | JESUS PINEDA |
| Shower Pan | 12/15/2025 | Corrections Issued | JESUS PINEDA |
| Underground Mechanical | 12/15/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 12/17/2025 | Approved | JESUS PINEDA |
| Sewer | 12/17/2025 | Approved | JESUS PINEDA |
| Shower Pan | 12/17/2025 | Approved | JESUS PINEDA |
| Final | 1/22/2026 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 1/22/2026 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 1/22/2026 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 1/22/2026 | Approved | JESUS PINEDA |
| Final | 1/28/2026 | Corrections Issued | JESUS PINEDA |
| Final | 2/3/2026 | Not Ready for Inspection | JESUS PINEDA |
| Final | 2/26/2026 | OK to Issue CofO | JESUS PINEDA |