3014-3016 S NORTON AVE 90018

Certificate Information: 3014-3016 S NORTON AVE 90018

Application / Permit
25014-10000-00726
Plan Check / Job No.
B25LA06256
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Convert existing attached garage to an ADU per LAMC 12.22 A.33(c) and (e), and add a new bathroom (44.5 sf) and a covered porch (83.5 sf) ****"COMPLY WITH DEPARTMENT ORDER effective date 10/07/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"****
Permit Issued
Issued on 6/4/2025
Issuing Office
Current Status
Issued on 6/4/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/20/2025 APPLICANT
Assigned to Plan Check Engineer 2/24/2025 HOOMAN HAJIZADEH
Corrections Issued 2/27/2025 HOOMAN HAJIZADEH
Applicant returned to address corrections 4/17/2025 HOOMAN HAJIZADEH
Applicant returned to address corrections 5/2/2025 JOHNPAUL ISIP
Applicant returned to address corrections 5/14/2025 HOOMAN HAJIZADEH
Applicant returned to address corrections 5/22/2025 REZA HAGHIGHAT
Plan Check Approved 6/3/2025 REZA HAGHIGHAT
Issued 6/4/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/3/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 4/3/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/3/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/7/2025 LEE GUILBEAUX
Sewer availability Cleared 4/7/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 6/23/2025 Corrections Issued LUIS CORRAL
PLUMBING-Rough 6/23/2025 Conditional Approval LUIS CORRAL
Wood Frame 6/23/2025 Corrections Issued LUIS CORRAL
ELECTRICAL-Rough 7/8/2025 Approved LUIS CORRAL
Interior/Exterior Lathing 7/8/2025 Approved LUIS CORRAL
Insulation 7/9/2025 Approved LUIS CORRAL
Drywall Nailing 7/10/2025 Not Ready for Inspection LUIS CORRAL
Green Building Rough 7/10/2025 Approved LUIS CORRAL
Interior/Exterior Lathing 7/10/2025 Approved LUIS CORRAL
Shower Pan 7/10/2025 Approved LUIS CORRAL
BUILDING-Rough-Frame 9/23/2025 Approved LUIS CORRAL
Drywall Nailing 9/23/2025 Approved LUIS CORRAL
ELECTRICAL-Final 9/23/2025 Not Ready for Inspection LUIS CORRAL
Final 9/23/2025 Not Ready for Inspection LUIS CORRAL
Footing/Foundation/Slab 9/23/2025 Approved LUIS CORRAL
Green Building Final 9/23/2025 Not Ready for Inspection LUIS CORRAL
Green Building Rough 9/23/2025 Approved LUIS CORRAL
HVAC-Final 9/23/2025 Not Ready for Inspection LUIS CORRAL
PLUMBING-Final 9/23/2025 Approved LUIS CORRAL
SGSOV-Seismic Gas S/O Valve 9/23/2025 SGSOV Approved LUIS CORRAL
Smoke Detectors 9/23/2025 Approved LUIS CORRAL
ELECTRICAL-Final 10/1/2025 Approved LUIS CORRAL
Final 10/1/2025 Not Ready for Inspection LUIS CORRAL
Green Building Final 10/1/2025 Corrections Issued LUIS CORRAL
HVAC-Final 10/1/2025 Approved LUIS CORRAL
Service/Power Release 10/1/2025 Approved LUIS CORRAL
Final 10/9/2025 Partial Approval LUIS CORRAL
Green Building Final 10/9/2025 Approved LUIS CORRAL