10742 W CHARNOCK ROAD 90034

Certificate Information: 10742 W CHARNOCK ROAD 90034

Application / Permit
25014-10000-00710
Plan Check / Job No.
B25LA06190
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 1ST FLOOR PATIO BELOW 2ND FLOOR RECREATION ROOM, STORAGE AND GARAGE INTO ADU WITH ADDITION PER ORDINANCE, LAMC 12.22 A.33 (c) and (e).
Permit Issued
Issued on 7/2/2025
Issuing Office
West Los Angeles
Current Status
Issued on 7/2/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/18/2025 APPLICANT
Assigned to Plan Check Engineer 2/21/2025 LAWRENCE QUIRANTE
Corrections Issued 2/22/2025 LAWRENCE QUIRANTE
Building Plans Picked Up 3/3/2025 APPLICANT
Applicant returned to address corrections 5/12/2025 KELVIN CHUONG
Plan Check Approved 5/29/2025 ADAM HEGAZI
Issued 7/2/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/15/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 4/15/2025 SAFA JAVANMARDI
Grading Pre-Inspection Cleared 4/22/2025 LANNY MERRICK
Eng Process Fee Ord 176,300 Cleared 4/23/2025 SAFA JAVANMARDI
Specific Plan Cleared 4/28/2025 PEDRO AYALA
Sewer availability Cleared 5/12/2025 SAFA JAVANMARDI

Contact Information

Contractor Mp Monte Construction Inc; Lic. No.: 979730-B 888 S FIGUEROA STREET #650      LOS ANGELES, CA 90017
Engineer Mirpoor,, Waheed Ahmad; Lic. No.: C94801 555 ROSEWOOD AVE   APT#308    CAMARILLO, CA 93010

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/18/2025 Approved TEMISTOCLES CAAL
PLUMBING-Rough 9/18/2025 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Final 10/3/2025 Corrections Issued KIRK SANDERS
PLUMBING-Rough 10/3/2025 Approved KIRK SANDERS
Sewer 10/3/2025 Approved KIRK SANDERS
Underground Mechanical 10/3/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 10/31/2025 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 10/31/2025 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 11/5/2025 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 11/5/2025 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 11/5/2025 Approved KIRK SANDERS
Underground Mechanical 11/5/2025 Partial Approval KIRK SANDERS
Wood Frame 11/5/2025 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 11/24/2025 Conditional Approval KIRK SANDERS
ELECTRICAL-Rough 11/24/2025 Corrections Issued KIRK SANDERS
Green Building Rough 11/24/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 11/24/2025 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 12/1/2025 Conditional Approval KIRK SANDERS
ELECTRICAL-Rough 12/1/2025 Partial Approval KIRK SANDERS
Insulation 12/1/2025 Partial Approval KIRK SANDERS
Special/Order Compliance 12/1/2025 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 12/17/2025 Approved KIRK SANDERS
Drywall Nailing 12/17/2025 Approved KIRK SANDERS
ELECTRICAL-Rough 12/17/2025 Approved KIRK SANDERS
Insulation 12/17/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 1/20/2026 Approved KIRK SANDERS
ELECTRICAL-Final 4/10/2026 Approved RYAN SALAZAR