7919 S CHASE AVE 90045

Certificate Information: 7919 S CHASE AVE 90045

Application / Permit
25014-10000-00704
Plan Check / Job No.
B25LA06147
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Proposal to build a one story addition to an existing one story SFD with attached garage.
Permit Issued
Issued on 4/19/2025
Issuing Office
Current Status
Issued on 4/19/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/18/2025 APPLICANT
Assigned to Plan Check Engineer 2/20/2025 VARAND SARKISIAN
Corrections Issued 2/25/2025 VARAND SARKISIAN
Quality Review Completed 2/27/2025 GARO TELMI
Plan Check Approved 4/18/2025 VARAND SARKISIAN
Issued 4/19/2025 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 3/7/2025 RUEL COLE
Roof/Waste drainage to street Cleared 3/8/2025 LIAM ODONOVAN
Trees in Parkway Cleared 3/8/2025 MIGUEL ORNELAS
Eng Process Fee Ord 176,300 Cleared 3/12/2025 LIAM ODONOVAN
Sewer availability Cleared 3/12/2025 LIAM ODONOVAN
Specific Plan Cleared 4/9/2025 RICHARD WOO
Grading Pre-Inspection Cleared 4/18/2025 VARAND SARKISIAN

Contact Information

Contractor Watson David Construction Inc; Lic. No.: 934184-B       ,
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/20/2025 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 10/18/2025 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 10/18/2025 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 10/18/2025 Corrections Issued CARLOS MATAMOROS
PLUMBING-Rough 10/18/2025 Partial Approval CARLOS MATAMOROS
Wood Frame 11/29/2025 Corrections Issued DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 1/24/2026 Partial Approval ANTHONY EGSON
Wood Frame 1/24/2026 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 2/7/2026 Not Ready for Inspection RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 2/7/2026 Partial Approval RUBEN RIVAS
Footing/Foundation/Slab 2/14/2026 Approved EUGENE CASSIDY
METHANE-Barrier 2/14/2026 Approved EUGENE CASSIDY
METHANE-Subgrade 2/14/2026 Approved EUGENE CASSIDY
PLUMBING-Rough 3/18/2026 Approved JESUS PINEDA
ELECTRICAL-Rough 3/20/2026 Partial Approval RUBEN RIVAS
HVAC-Rough 3/20/2026 Partial Approval RUBEN RIVAS
Shower Pan 3/23/2026 Approved JESUS PINEDA
BUILDING-Rough-Frame 4/3/2026 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Rough 4/3/2026 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 4/3/2026 Corrections Issued JESUS PINEDA
HVAC-Rough 4/3/2026 Corrections Issued JESUS PINEDA
Interior/Exterior Lathing 4/3/2026 Corrections Issued JESUS PINEDA
Verify Sprinkler Sign Off 4/3/2026 Approved JESUS PINEDA
HVAC-Rough 4/8/2026 Partial Approval EUGENE CASSIDY
Wood Frame 4/8/2026 Partial Approval EUGENE CASSIDY
Insulation 4/21/2026 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 4/24/2026 Approved ANTHONY EGSON
HVAC-Rough 4/24/2026 Approved ANTHONY EGSON
Insulation 4/24/2026 Approved ANTHONY EGSON
Drywall Nailing 5/4/2026 Approved JESUS PINEDA