5452 N COSTELLO AVE 91401
Certificate Information: 5452 N COSTELLO AVE 91401
- Application / Permit
- 25014-10000-00701
- Plan Check / Job No.
- B25LA06113
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN. ADDITION AND REMODEL (E) SFD W/ATTACHED GARAGE. PER WFPP.
- Permit Issued
- Issued on 6/25/2025
- Issuing Office
- Current Status
- CofO Issued on 1/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2025 | ALFREDO JARA |
| Corrections Issued | 2/22/2025 | ALFREDO JARA |
| Applicant returned to address corrections | 4/17/2025 | ALFREDO JARA |
| Applicant returned to address corrections | 4/28/2025 | ALFREDO JARA |
| Plan Check Approved | 5/11/2025 | ALFREDO JARA |
| Plan Check Approved | 5/27/2025 | ALFREDO JARA |
| Issued | 6/25/2025 | APPLICANT |
| CofO in Progress | 12/31/2025 | RYAN SALAZAR |
| Permit Finaled | 1/10/2026 | RUBEN SALAS |
| CofO Issued | 1/10/2026 | RUBEN SALAS |
| Permit Finaled | 1/10/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/3/2025 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2025 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/30/2025 | Partial Inspection | RYAN SALAZAR |
| Footing/Foundation/Slab | 7/15/2025 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2025 | Partial Approval | MICHAEL CORTEZ |
| PLUMBING-Rough | 7/22/2025 | Partial Approval | MICHAEL CORTEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2025 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 8/25/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 8/25/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 8/25/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 8/25/2025 | Approved | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 8/25/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 8/27/2025 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 9/2/2025 | Partial Approval | RYAN SALAZAR |
| Insulation | 9/5/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 9/11/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/11/2025 | Approved | RYAN SALAZAR |
| Final | 12/19/2025 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 12/19/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 12/19/2025 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 12/19/2025 | Approved | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 1/2/2026 | Conditional Approval | RYAN SALAZAR |
| Final | 1/2/2026 | OK to Issue CofO | RYAN SALAZAR |