5452 N COSTELLO AVE 91401

Certificate Information: 5452 N COSTELLO AVE 91401

Application / Permit
25014-10000-00701
Plan Check / Job No.
B25LA06113
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. ADDITION AND REMODEL (E) SFD W/ATTACHED GARAGE. PER WFPP.
Permit Issued
Issued on 6/25/2025
Issuing Office
Current Status
CofO Issued on 1/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2025 APPLICANT
Assigned to Plan Check Engineer 2/21/2025 ALFREDO JARA
Corrections Issued 2/22/2025 ALFREDO JARA
Applicant returned to address corrections 4/17/2025 ALFREDO JARA
Applicant returned to address corrections 4/28/2025 ALFREDO JARA
Plan Check Approved 5/11/2025 ALFREDO JARA
Plan Check Approved 5/27/2025 ALFREDO JARA
Issued 6/25/2025 APPLICANT
CofO in Progress 12/31/2025 RYAN SALAZAR
Permit Finaled 1/10/2026 RUBEN SALAS
CofO Issued 1/10/2026 RUBEN SALAS
Permit Finaled 1/10/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/3/2025 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 5/6/2025 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/30/2025 Partial Inspection RYAN SALAZAR
Footing/Foundation/Slab 7/15/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 7/22/2025 Partial Approval MICHAEL CORTEZ
PLUMBING-Rough 7/22/2025 Partial Approval MICHAEL CORTEZ
Floor/Roof Diaphrgm/Shear Wall 7/23/2025 Partial Approval GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 8/25/2025 Approved RYAN SALAZAR
ELECTRICAL-Rough 8/25/2025 Approved RYAN SALAZAR
Green Building Rough 8/25/2025 Approved RYAN SALAZAR
PLUMBING-Rough 8/25/2025 Approved RYAN SALAZAR
Rough-Elec/Plmb/HVAC 8/25/2025 Approved RYAN SALAZAR
Shower Pan 8/27/2025 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 9/2/2025 Partial Approval RYAN SALAZAR
Insulation 9/5/2025 Approved RYAN SALAZAR
Drywall Nailing 9/11/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 9/11/2025 Approved RYAN SALAZAR
Final 12/19/2025 Corrections Issued RYAN SALAZAR
Green Building Final 12/19/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/19/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 12/19/2025 Approved RYAN SALAZAR
Deputy Drilled-In Anchors 1/2/2026 Conditional Approval RYAN SALAZAR
Final 1/2/2026 OK to Issue CofO RYAN SALAZAR