5541 E TEMPLETON ST 90032
Certificate Information: 5541 E TEMPLETON ST 90032
- Application / Permit
- 25014-10000-00678
- Plan Check / Job No.
- B24LA38658
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: REMODEL OF (E) SFD, CONVERT PORTION OF (E) SFD TO ATTACHED STORAGE, REPLACE (E) WINDOWS PER PLAN, WORK PER ENGINEERED DESIGN.
- Permit Issued
- Issued on 5/22/2025
- Issuing Office
- Current Status
- CofO Issued on 5/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/19/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2025 | OMAR GARNICA |
| Plan Check Approved | 2/25/2025 | OMAR GARNICA |
| Issued | 5/22/2025 | APPLICANT |
| CofO in Progress | 3/2/2026 | CHARLES BOGHOSKHAN |
| CofO in Progress | 3/2/2026 | CHARLES BOGHOSKHAN |
| CofO in Progress | 5/20/2026 | LILIANA PORTILLO |
| Permit Finaled | 5/21/2026 | DEROLD HAUFF |
| CofO Issued | 5/21/2026 | DEROLD HAUFF |
| Permit Finaled | 5/21/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Jorgensen - Reeve Builders Inc; Lic. No.: 876216-B | , |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/12/2025 | Partial Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 7/10/2025 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/21/2025 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 10/21/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 12/10/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 12/10/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 12/10/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 12/23/2025 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 12/23/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 1/8/2026 | Approved | LILIANA PORTILLO |
| Insulation | 1/8/2026 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 1/15/2026 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/15/2026 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 2/18/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 2/18/2026 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 2/18/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 2/18/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 2/18/2026 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 2/18/2026 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 2/20/2026 | Approved | LILIANA PORTILLO |
| Final | 2/20/2026 | Conditional Approval | LILIANA PORTILLO |
| HVAC-Final | 2/20/2026 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 2/20/2026 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 2/20/2026 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 2/20/2026 | Approved | LILIANA PORTILLO |
| Final | 3/10/2026 | Corrections Issued | LILIANA PORTILLO |
| Final | 5/14/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 5/19/2026 | OK to Issue CofO | LILIANA PORTILLO |