11632 W VICTORIA AVE 90066

Certificate Information: 11632 W VICTORIA AVE 90066

Application / Permit
25014-10000-00660
Plan Check / Job No.
B25LA05738
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN NEW 1ST FLOOR ADDITION TO (E) GARAGE AND 2ND FLOOR ADU ADDITION ON TOP OF (E) GARAGE PER CITY ORDINACE WORK DONE PER ENGINEER DESIGN
Permit Issued
Issued on 5/12/2025
Issuing Office
Current Status
Issued on 5/12/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/15/2025 APPLICANT
Assigned to Plan Check Engineer 2/20/2025 KHUONG TRUONG
Corrections Issued 2/26/2025 KHUONG TRUONG
Quality Review Completed 2/26/2025 GARO TELMI
Plan Check Approved 4/2/2025 KHUONG TRUONG
Issued 5/12/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/27/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 3/10/2025 DARIN LAM
Sewer availability Cleared 3/10/2025 DARIN LAM
Grading Pre-Inspection Cleared 3/10/2025 VASIL MIHALEV
Roof/Waste drainage to street Cleared 3/11/2025 DARIN LAM
Specific Plan Cleared 3/17/2025 JOSHUA JONES

Contact Information

Contractor Cr Builders Llc; Lic. No.: 1131278-B       ,
Engineer Pinzon,, Eduardo Andres; Lic. No.: NA74869       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/26/2025 Approved WILBER ROSALES
Excavation/Setback/Form/Re-Bar 6/26/2025 Corrections Issued WILBER ROSALES
Pre-Inspection 6/26/2025 Partial Inspection WILBER ROSALES
Excavation/Setback/Form/Re-Bar 6/30/2025 Corrections Issued WILBER ROSALES
Deputy Steel/Welding 7/18/2025 Conditional Approval WILBER ROSALES
Excavation/Setback/Form/Re-Bar 7/18/2025 Approved WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 7/18/2025 Corrections Issued WILBER ROSALES
Deputy Wood Construction 7/22/2025 Conditional Approval KIRK SANDERS
BUILDING-Rough-Frame 7/23/2025 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 7/23/2025 Conditional Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/24/2025 Partial Approval EVAN COOPER
ELECTRICAL-Rough 10/21/2025 Corrections Issued MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 10/21/2025 Corrections Issued MICHAEL ALLEN
PLUMBING-Rough 10/21/2025 Corrections Issued MICHAEL ALLEN
BUILDING-Rough-Frame 10/30/2025 Partial Approval MICHAEL ALLEN
ELECTRICAL-Rough 10/30/2025 Approved MICHAEL ALLEN
Gas Test 10/30/2025 Approved MICHAEL ALLEN
HVAC-Rough 10/30/2025 Approved MICHAEL ALLEN
PLUMBING-Rough 10/30/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 11/6/2025 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 11/12/2025 Not Ready for Inspection KIRK SANDERS
Shower Pan 11/12/2025 Not Ready for Inspection KIRK SANDERS
Deputy Steel/Welding 11/13/2025 Conditional Approval KIRK SANDERS
BUILDING-Rough-Frame 12/1/2025 Approved MICHAEL ALLEN
Green Building Rough 12/1/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 12/1/2025 Partial Approval MICHAEL ALLEN
Insulation 12/9/2025 Conditional Approval EUGENE CASSIDY
Interior/Exterior Lathing 12/9/2025 Approved EUGENE CASSIDY
Shower Pan 12/9/2025 Approved EUGENE CASSIDY
Drywall Nailing 12/19/2025 Partial Approval KIRK SANDERS
Final 12/19/2025 Corrections Issued KIRK SANDERS
Special/Order Compliance 12/19/2025 Corrections Issued KIRK SANDERS
Insulation 4/15/2026 Approved ANDREW NAVE
Special/Order Compliance 6/10/2026 Corrections Issued KIRK SANDERS