11500 W CALVERT ST 91606

Certificate Information: 11500 W CALVERT ST 91606

Application / Permit
25014-10000-00638
Plan Check / Job No.
B25LA05520
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO EXISTING SFD
Permit Issued
Issued on 2/27/2025
Issuing Office
Metro
Current Status
CofO Issued on 8/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2025 APPLICANT
Assigned to Plan Check Engineer 2/18/2025 FERNANDO FLORES
Corrections Issued 2/20/2025 FERNANDO FLORES
Plan Check Approved 2/26/2025 DANIEL SANJUAN
Issued 2/27/2025 APPLICANT
CofO in Progress 5/19/2025 JOSE AVILA
Permit Finaled 8/28/2025 RUBEN SALAS
CofO Issued 8/28/2025 RUBEN SALAS
Permit Finaled 8/28/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/25/2025 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 2/26/2025 EDGAR ALCARAZ
Sewer availability Cleared 2/26/2025 NAZILA NOORIFAR

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/5/2025 Approved ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 3/12/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 3/12/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Wood Frame 3/18/2025 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 3/19/2025 Approved JOSE AVILA
Wood Frame 3/19/2025 Approved JOSE AVILA
Wood Frame 3/20/2025 Partial Approval JOSE AVILA
ELECTRICAL-Rough 4/1/2025 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 Approved JOSE AVILA
ELECTRICAL-Rough 4/4/2025 Approved JOSE AVILA
HVAC-Rough 4/4/2025 Approved JOSE AVILA
PLUMBING-Rough 4/4/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 4/8/2025 Approved JOSE AVILA
Interior/Exterior Lathing 4/9/2025 Approved JOSE AVILA
Shower Pan 4/10/2025 Partial Inspection JOSE AVILA
Interior/Exterior Lathing 4/11/2025 Approved JOSE AVILA
Shower Pan 4/11/2025 Approved JOSE AVILA
Drywall Nailing 4/15/2025 Approved JOSE AVILA
Interior/Exterior Lathing 4/15/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 5/9/2025 Approved JOSE AVILA
ELECTRICAL-Final 5/9/2025 Approved JOSE AVILA
Green Building Final 5/9/2025 Approved JOSE AVILA
Green Building Rough 5/9/2025 Approved JOSE AVILA
HVAC-Final 5/9/2025 Corrections Issued JOSE AVILA
PLUMBING-Final 5/9/2025 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 5/9/2025 SGSOV Not Ready JOSE AVILA
HVAC-Final 5/13/2025 Approved JOSE AVILA
PLUMBING-Final 5/13/2025 Corrections Issued JOSE AVILA
Final 5/14/2025 OK to Issue CofO JOSE AVILA
SGSOV-Seismic Gas S/O Valve 5/14/2025 SGSOV Approved JOSE AVILA
Smoke Detectors 5/14/2025 Approved JOSE AVILA