2219 S ORANGE DR 90016
Certificate Information: 2219 S ORANGE DR 90016
- Application / Permit
- 25014-10000-00635
- Plan Check / Job No.
- B25LA05477
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. (N) ONE STORY 20' X 20' 11" ADDITION TO (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/25/2025
- Issuing Office
- Current Status
- Issued on 3/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/19/2025 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 2/20/2025 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 3/20/2025 | NAREG ATARIAN |
| Plan Check Approved | 3/24/2025 | NAREG ATARIAN |
| Issued | 3/25/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/4/2025 | JUSTIN BICOL |
| Sewer availability | Cleared | 3/4/2025 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2025 | JUSTIN BICOL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 1543 HAWTHORNE, CA 90251 |
| Engineer | Hamilton,, John O; Lic. No.: NA53284 | , |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/21/2025 | Approved | LUIS CORRAL |
| Footing/Foundation/Slab | 8/21/2025 | Approved | LUIS CORRAL |
| BUILDING-Rough-Frame | 10/9/2025 | Partial Approval | LUIS CORRAL |
| Insulation | 10/9/2025 | Partial Approval | LUIS CORRAL |
| PLUMBING-Rough | 10/9/2025 | Approved | LUIS CORRAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2025 | Approved | LUIS CORRAL |
| Deputy Wood Construction | 10/23/2025 | Approved | LUIS CORRAL |
| ELECTRICAL-Rough | 11/19/2025 | Approved | LUIS CORRAL |
| PLUMBING-Rough | 11/19/2025 | Conditional Approval | LUIS CORRAL |
| Wood Frame | 11/19/2025 | Approved | LUIS CORRAL |
| ELECTRICAL-Rough | 11/25/2025 | Approved | LUIS CORRAL |
| HVAC-Rough | 11/25/2025 | Approved | LUIS CORRAL |
| Insulation | 11/25/2025 | Approved | LUIS CORRAL |
| Interior/Exterior Lathing | 11/25/2025 | Approved | LUIS CORRAL |
| PLUMBING-Rough | 11/25/2025 | Approved | LUIS CORRAL |
| Drywall Nailing | 12/4/2025 | Approved | LUIS CORRAL |
| Green Building Rough | 12/4/2025 | Approved | LUIS CORRAL |
| Interior/Exterior Lathing | 2/18/2026 | Approved | LUIS CORRAL |
| Shower Pan | 2/18/2026 | Conditional Approval | LUIS CORRAL |