3443 S SEPULVEDA BLVD 90034
Certificate Information: 3443 S SEPULVEDA BLVD 90034
- Application / Permit
- 25014-10000-00633
- Plan Check / Job No.
- B25LA05452
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- CHANGE OF USE OF (E) ONE STORY TYPE V-B ART STUDIO TO RETAIL/ GROCERY STORE & EXTERIOR T.I & INSTALL CANTILEVER CANOPY TRELLISES & NEW STOREFRONT ( BUILDING OCCUPIED WITH SPRINKLER SYSYTEM & NO PARKING CHANGED). ( INTERIOR T.I UNDER SEPARATE PERMIT)
- Permit Issued
- Issued on 10/1/2025
- Issuing Office
- Metro
- Current Status
- Issued on 10/1/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2025 | GARO TELMI |
| Assigned to Zoning Architect | 2/20/2025 | ERIC ROMERO |
| Corrections Issued | 2/27/2025 | GARO TELMI |
| Quality Review Completed | 3/3/2025 | KEN GILL |
| Building Plans Picked Up | 3/6/2025 | APPLICANT |
| Applicant returned to address corrections | 4/2/2025 | GARO TELMI |
| Disabled Access Plans Picked Up | 4/2/2025 | APPLICANT |
| Green Plans Picked Up | 4/7/2025 | APPLICANT |
| Applicant returned to address corrections | 5/6/2025 | GARO TELMI |
| Applicant returned to address corrections | 6/12/2025 | GARO TELMI |
| Applicant returned to address corrections | 7/2/2025 | GARO TELMI |
| Plan Check Approved | 10/1/2025 | GARO TELMI |
| Issued | 10/1/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/26/2025 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 3/26/2025 | HISASHI KOBAYAKAWA |
| Food Service Establishment | Cleared | 4/18/2025 | LUIS LUVANO |
| Low Impact Development (LID) | Cleared | 4/28/2025 | ERNEST TSE |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2025 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 5/5/2025 | LIAM ODONOVAN |
| Green Code | Cleared | 7/9/2025 | GARO TELMI |
| DAS Clearance | Cleared | 8/15/2025 | GARO TELMI |
| Driveway location | Cleared | 9/5/2025 | PEDRO AYALA |
| Internal circulation | Cleared | 9/5/2025 | PEDRO AYALA |
| Miscellaneous | Cleared | 9/5/2025 | WALLIE JONG |
| Permit | Cleared | 9/5/2025 | WALLIE JONG |
| Specific Plan | Cleared | 9/5/2025 | PEDRO AYALA |
| CPC | Cleared | 9/24/2025 | FIPE LEILUA |
| Comm Cor/Mini-Mall | Cleared | 9/24/2025 | FIPE LEILUA |
| Comm Cor/Mini-Mall | Cleared | 9/24/2025 | FIPE LEILUA |
| Miscellaneous | Cleared | 9/24/2025 | FIPE LEILUA |
| ZA Case | Cleared | 9/24/2025 | FIPE LEILUA |
| ZA Case | Cleared | 9/24/2025 | FIPE LEILUA |
| Zoning Plan Check | Cleared | 9/25/2025 | ERIC ROMERO |
| GPI Written Notices | Cleared | 10/1/2025 | AL GAMBLE |
| Grading Pre-Inspection | Cleared | 10/1/2025 | AL GAMBLE |
Contact Information
| Architect | Soares,, Christen F; Lic. No.: C32372 | 711 MARKET ST 2ND FLR SAN FRANCISCO, CA 94103 |
| Contractor | Gautreau Art Inc; Lic. No.: 370609-B | 8210 KATELLA AVENUE SUITE I STANTON, CA 90680 |
| Engineer | Choi,, Michael; Lic. No.: C67851 | 1221 N ORANGE DR 217 LOS ANGELES, CA 90038 |
| Engineer | Treat,, Kevin; Lic. No.: S4947 | 3527 MOUNT DIABLO BLVD #242 LAFAYETTE, CA 94549 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/27/2025 | Approved | FARHAD DADBIN |
| Deputy Drilled-In Anchors | 11/4/2025 | Approved | FARHAD DADBIN |
| Deputy Reinf. Concrete | 11/4/2025 | Approved | FARHAD DADBIN |
| Footing/Foundation/Slab | 11/4/2025 | Partial Approval | FARHAD DADBIN |
| Grading Pre-Inspection | 11/4/2025 | Partial Approval | FARHAD DADBIN |
| Structural Steel Frame | 11/4/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Deputy Reinf. Concrete | 11/7/2025 | Approved | FARHAD DADBIN |
| Reinforced Concrete Frame | 11/7/2025 | Partial Approval | FARHAD DADBIN |
| Deputy Shotcrete | 11/10/2025 | Conditional Approval | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 11/12/2025 | Partial Approval | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 11/26/2025 | Partial Approval | FARHAD DADBIN |
| Reinforced Masonry Frame | 12/4/2025 | Partial Approval | FARHAD DADBIN |
| Masonry Wall/Backfill | 12/9/2025 | Partial Approval | FARHAD DADBIN |
| Light Gage Steel Frame | 12/22/2025 | Partial Approval | FARHAD DADBIN |
| Deputy Wood Construction | 1/5/2026 | Conditional Approval | FARHAD DADBIN |
| Light Gage Steel Frame | 1/5/2026 | Partial Approval | FARHAD DADBIN |
| Green Building Rough | 1/6/2026 | Approved | FARHAD DADBIN |
| Wood Frame | 1/6/2026 | Partial Approval | FARHAD DADBIN |
| Drywall Nailing | 1/13/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Insulation | 1/13/2026 | Partial Approval | FARHAD DADBIN |
| Insulation | 1/14/2026 | Partial Approval | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2026 | Partial Approval | FARHAD DADBIN |
| Drywall Nailing | 1/20/2026 | Partial Approval | FARHAD DADBIN |
| Deputy Steel/Welding | 1/22/2026 | Conditional Approval | FARHAD DADBIN |
| Deputy Drilled-In Anchors | 2/19/2026 | Approved | FARHAD DADBIN |
| Footing/Foundation/Slab | 2/19/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Deputy Drilled-In Anchors | 2/24/2026 | Approved | FARHAD DADBIN |
| Deputy Reinf. Concrete | 2/24/2026 | Approved | FARHAD DADBIN |
| Footing/Foundation/Slab | 2/26/2026 | Partial Approval | FARHAD DADBIN |
| Deputy Drilled-In Anchors | 3/3/2026 | Conditional Approval | FARHAD DADBIN |
| Deputy Reinf. Concrete | 3/3/2026 | Conditional Approval | FARHAD DADBIN |
| Deputy Reinf. Concrete | 3/5/2026 | Approved | FARHAD DADBIN |
| Deputy Reinf. Concrete | 3/6/2026 | Approved | FARHAD DADBIN |
| Deputy Drilled-In Anchors | 3/10/2026 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 3/10/2026 | Conditional Approval | PAUL DAVIDSON |
| Light Gage Steel Frame | 3/18/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Light Gage Steel Frame | 3/20/2026 | Partial Approval | FARHAD DADBIN |
| Structural Steel Frame | 4/8/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Light Gage Steel Frame | 4/20/2026 | Partial Approval | FARHAD DADBIN |
| Light Gage Steel Frame | 4/22/2026 | Partial Approval | FARHAD DADBIN |
| Deputy Reinf. Concrete | 6/24/2026 | Conditional Approval | FARHAD DADBIN |