4434 N BAKMAN AVE 91602

Certificate Information: 4434 N BAKMAN AVE 91602

Application / Permit
25014-10000-00626
Plan Check / Job No.
B25LA05420
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ADU WITH ADDITION 157 S.F.
Permit Issued
Issued on 3/27/2025
Issuing Office
Current Status
CofO Issued on 12/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2025 APPLICANT
Assigned to Plan Check Engineer 2/18/2025 FERNANDO FLORES
Corrections Issued 2/19/2025 FERNANDO FLORES
Building Plans Picked Up 2/21/2025 APPLICANT
Plan Check Approved 3/26/2025 CRISTINA SALAZAR
Issued 3/27/2025 APPLICANT
CofO in Progress 12/1/2025 JAVIER RAMOS JR
Permit Finaled 12/26/2025 RUBEN SALAS
CofO Issued 12/26/2025 RUBEN SALAS
Permit Finaled 12/26/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/25/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/25/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 2/25/2025 LEE GUILBEAUX
Sewer availability Cleared 2/25/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 2/25/2025 LEE GUILBEAUX
ZI Cleared 3/24/2025 MAYELA VILLA

Contact Information

Contractor Ene Builders; Lic. No.: 1113906-B 21434 WYANDOTTE STREET      CANOGA PARK, CA 91303
Engineer Madero,, Fidencio; Lic. No.: C81695 PO BOX 40237      DOWNEY, CA 90239

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/7/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 4/7/2025 Partial Approval JAVIER RAMOS JR
Sewer 4/7/2025 Approved JAVIER RAMOS JR
Underground Mechanical 4/7/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 4/8/2025 No Access for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/18/2025 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 4/18/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/18/2025 Partial Approval JAVIER RAMOS JR
HVAC-Rough 4/18/2025 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 4/18/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 4/28/2025 Partial Approval JAVIER RAMOS JR
Green Building Rough 4/28/2025 Approved JAVIER RAMOS JR
HVAC-Rough 4/28/2025 Approved JAVIER RAMOS JR
Underground Mechanical 4/28/2025 Partial Approval JAVIER RAMOS JR
Insulation 5/1/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 5/1/2025 Approved JAVIER RAMOS JR
Drywall Nailing 5/6/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/6/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 5/6/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 11/7/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 11/7/2025 Partial Inspection JAVIER RAMOS JR
Final 11/7/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 11/7/2025 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 11/7/2025 Approved JAVIER RAMOS JR
MERV13>=Final 11/7/2025 Approved JAVIER RAMOS JR
MERV13>=Rough 11/7/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 11/7/2025 Partial Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 11/7/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 11/7/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 11/18/2025 Not Ready for Inspection JACK KARGODORIAN
Final 11/18/2025 Corrections Issued JACK KARGODORIAN
Green Building Final 11/18/2025 Not Ready for Inspection JACK KARGODORIAN
HVAC-Final 11/18/2025 Approved JACK KARGODORIAN
PLUMBING-Final 11/18/2025 Approved JACK KARGODORIAN
ELECTRICAL-Final 12/1/2025 Approved JAVIER RAMOS JR
Final 12/1/2025 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 12/1/2025 Approved JAVIER RAMOS JR