4434 N BAKMAN AVE 91602
Certificate Information: 4434 N BAKMAN AVE 91602
- Application / Permit
- 25014-10000-00626
- Plan Check / Job No.
- B25LA05420
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ADU WITH ADDITION 157 S.F.
- Permit Issued
- Issued on 3/27/2025
- Issuing Office
- Current Status
- CofO Issued on 12/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2025 | FERNANDO FLORES |
| Corrections Issued | 2/19/2025 | FERNANDO FLORES |
| Building Plans Picked Up | 2/21/2025 | APPLICANT |
| Plan Check Approved | 3/26/2025 | CRISTINA SALAZAR |
| Issued | 3/27/2025 | APPLICANT |
| CofO in Progress | 12/1/2025 | JAVIER RAMOS JR |
| Permit Finaled | 12/26/2025 | RUBEN SALAS |
| CofO Issued | 12/26/2025 | RUBEN SALAS |
| Permit Finaled | 12/26/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/25/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 2/25/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/25/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 2/25/2025 | LEE GUILBEAUX |
| ZI | Cleared | 3/24/2025 | MAYELA VILLA |
Contact Information
| Contractor | Ene Builders; Lic. No.: 1113906-B | 21434 WYANDOTTE STREET CANOGA PARK, CA 91303 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | PO BOX 40237 DOWNEY, CA 90239 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/7/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/7/2025 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 4/7/2025 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 4/7/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/8/2025 | No Access for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/18/2025 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 4/18/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2025 | Partial Approval | JAVIER RAMOS JR |
| HVAC-Rough | 4/18/2025 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/18/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/28/2025 | Partial Approval | JAVIER RAMOS JR |
| Green Building Rough | 4/28/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 4/28/2025 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 4/28/2025 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 5/1/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/1/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 5/6/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/6/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 11/7/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 11/7/2025 | Partial Inspection | JAVIER RAMOS JR |
| Final | 11/7/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 11/7/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 11/7/2025 | Approved | JAVIER RAMOS JR |
| MERV13>=Final | 11/7/2025 | Approved | JAVIER RAMOS JR |
| MERV13>=Rough | 11/7/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 11/7/2025 | Partial Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 11/7/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 11/7/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 11/18/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 11/18/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 11/18/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Final | 11/18/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 11/18/2025 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 12/1/2025 | Approved | JAVIER RAMOS JR |
| Final | 12/1/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 12/1/2025 | Approved | JAVIER RAMOS JR |