532 W 8TH ST 1-2 90731
Certificate Information: 532 W 8TH ST 1-2 90731
- Application / Permit
- 25014-10000-00621
- Plan Check / Job No.
- B25LA05345
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan - 2ND FLOOR (2) UNIT ADU (400 SF EACH) ADDITION TO EXISITNG 1 STORY GARAGE PER CA GOVT CODE 66323(A)(4)
- Permit Issued
- Issued on 10/2/2025
- Issuing Office
- Current Status
- Issued on 10/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2025 | STARR CHEN |
| Corrections Issued | 3/12/2025 | STARR CHEN |
| Quality Review Completed | 3/13/2025 | EUGENE BARBEAU |
| Applicant returned to address corrections | 5/13/2025 | STARR CHEN |
| Applicant returned to address corrections | 7/16/2025 | STARR CHEN |
| Plan Check Approved | 8/14/2025 | STARR CHEN |
| Issued | 10/2/2025 | APPLICANT |
Permit Application Clearance Information
| "D" conditions | Cleared | 3/13/2025 | JACQUELINE TORRES |
| Address approval | Cleared | 3/17/2025 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 3/17/2025 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2025 | ERIK BEASLEY |
| Sewer availability | Cleared | 3/21/2025 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 4/14/2025 | JERRY KAO |
| Historic Resource Verification | Cleared | 4/30/2025 | RAFAEL FONTES |
| Community Plan Implem. Overlay | Cleared | 7/8/2025 | NORALI MARTINEZ |
| Redevelopment Project Area | Cleared | 7/8/2025 | YASMINE BASHIRI |
Contact Information
| Contractor | Neeraj Mittal; Lic. No.: 1127454-B | , |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 28025 DOROTHY DR STE 202 AGOURA HILLS, CA 91301 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/29/2025 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 10/29/2025 | Corrections Issued | BEN MOLSTAD |
| Excavation/Setback/Form/Re-Bar | 10/31/2025 | Conditional Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 10/31/2025 | Conditional Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2025 | Conditional Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 11/21/2025 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2025 | Conditional Approval | JOSEPH MCGARRY |
| Special/Order Compliance | 12/5/2025 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 1/28/2026 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 1/28/2026 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 1/28/2026 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 1/28/2026 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 1/28/2026 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 1/28/2026 | Approved | JOSEPH MCGARRY |
| Sewer | 1/28/2026 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 1/28/2026 | Corrections Issued | JOSEPH MCGARRY |
| Insulation | 3/5/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 3/5/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| Insulation | 3/6/2026 | Conditional Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 3/6/2026 | Conditional Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/8/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| Drywall Nailing | 4/8/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/9/2026 | Corrections Issued | JOSEPH MCGARRY |
| HVAC-Rough | 4/9/2026 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/17/2026 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 4/17/2026 | Approved | JOSEPH MCGARRY |
| Insulation | 4/17/2026 | Approved | JOSEPH MCGARRY |
| Shower Pan | 4/17/2026 | Corrections Issued | JOSEPH MCGARRY |
| Shower Pan | 4/23/2026 | Corrections Issued | JOSEPH MCGARRY |
| Shower Pan | 4/28/2026 | Conditional Approval | JOSEPH MCGARRY |
| Special/Order Compliance | 5/15/2026 | Corrections Issued | JOSEPH MCGARRY |
| Underground Mechanical | 5/15/2026 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 6/29/2026 | Approved | JOSEPH MCGARRY |