2814 S HADDINGTON DR 90064
Certificate Information: 2814 S HADDINGTON DR 90064
- Application / Permit
- 25014-10000-00609
- Plan Check / Job No.
- B25LA05219
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: Ground and 2nd floor addition and major remodel to ground level to existing 2-story Single family dwelling
- Permit Issued
- Issued on 4/23/2025
- Issuing Office
- Current Status
- CofO Issued on 5/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2025 | KHEDER ALRAZAA |
| Corrections Issued | 3/4/2025 | KHEDER ALRAZAA |
| Quality Review Completed | 3/4/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 3/21/2025 | KHEDER ALRAZAA |
| Plan Check Approved | 4/23/2025 | KHEDER ALRAZAA |
| Issued | 4/23/2025 | APPLICANT |
| CofO in Progress | 5/27/2026 | ASHLEY THOMPSON |
| Permit Finaled | 5/28/2026 | RICHARD STEINBACH |
| CofO Issued | 5/28/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/28/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/6/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2025 | DARIN LAM |
| Grading Pre-Inspection | Cleared | 3/7/2025 | VASIL MIHALEV |
| Roof/Waste drainage to street | Cleared | 3/13/2025 | DARIN LAM |
| GPI Written Notices | Cleared | 4/23/2025 | KHEDER ALRAZAA |
Contact Information
| Architect | Abramson,, Trevor David; Lic. No.: C17597 | 5171 W JEFFERSON BLVD. LOS ANGELES, CA 90016 |
| Contractor | Owner-Builder | , |
| Engineer | Castro,, Ivan; Lic. No.: C84846 | 750 OTAY LAKES ROAD #202 CHULA VISTA, CA 91910 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/8/2025 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2025 | Corrections Issued | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2025 | Partial Approval | ASHLEY THOMPSON |
| Insulation | 5/27/2025 | Partial Approval | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2025 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2025 | Partial Approval | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2025 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Rough | 8/12/2025 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 8/12/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2025 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Rough | 8/14/2025 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 8/14/2025 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 8/21/2025 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2025 | Partial Approval | ASHLEY THOMPSON |
| METHANE-Rough | 8/21/2025 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 8/21/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 9/18/2025 | Partial Approval | ASHLEY THOMPSON |
| Shower Pan | 9/18/2025 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 9/23/2025 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 9/25/2025 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 9/25/2025 | Corrections Issued | ASHLEY THOMPSON |
| Deputy Wood Construction | 9/26/2025 | Conditional Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 9/30/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Rough | 9/30/2025 | Approved | ASHLEY THOMPSON |
| Insulation | 9/30/2025 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 10/15/2025 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 10/15/2025 | Partial Approval | ASHLEY THOMPSON |
| Insulation | 10/15/2025 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 10/17/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 3/18/2026 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Final | 4/10/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 4/10/2026 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 5/6/2026 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 5/12/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Final | 5/12/2026 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 5/12/2026 | Approved | ASHLEY THOMPSON |
| Green Building Final | 5/12/2026 | Approved | ASHLEY THOMPSON |
| METHANE-Barrier | 5/12/2026 | Approved | ASHLEY THOMPSON |
| METHANE-Subgrade | 5/12/2026 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 5/12/2026 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 5/12/2026 | Approved | ASHLEY THOMPSON |
| Final | 5/27/2026 | OK to Issue CofO | ASHLEY THOMPSON |
| Service/Power Release | 5/27/2026 | Approved | ASHLEY THOMPSON |