3126-3128 S COOLIDGE AVE 90066
Certificate Information: 3126-3128 S COOLIDGE AVE 90066
- Application / Permit
- 25014-10000-00602
- Plan Check / Job No.
- B25LA05191
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: ATTACHED ACCESSORY DWELLING UNIT ADDITION TO (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE PER LAMC 12.22 A.33 (c) and (e)
- Permit Issued
- Issued on 3/31/2025
- Issuing Office
- Current Status
- CofO Issued on 2/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2025 | DANIEL YIP |
| Corrections Issued | 2/15/2025 | DANIEL YIP |
| Applicant returned to address corrections | 2/28/2025 | SUNMIN LEE |
| Plan Check Approved | 3/27/2025 | SUNMIN LEE |
| Issued | 3/31/2025 | APPLICANT |
| CofO in Progress | 2/11/2026 | ARAM AVEDISIAN |
| Permit Finaled | 2/17/2026 | RICHARD STEINBACH |
| CofO Issued | 2/17/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/17/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/20/2025 | VASIL MIHALEV |
| Address approval | Cleared | 2/22/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2025 | DARIN LAM |
| Sewer availability | Cleared | 2/25/2025 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 2/27/2025 | DARIN LAM |
| Construction within easement | Cleared | 3/25/2025 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/24/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 6/27/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 7/14/2025 | Partial Approval | WILBER ROSALES |
| Insulation | 7/14/2025 | Partial Approval | WILBER ROSALES |
| PLUMBING-Rough | 7/14/2025 | Partial Approval | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2025 | Conditional Approval | KIRK SANDERS |
| Special/Order Compliance | 8/14/2025 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 9/19/2025 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 9/19/2025 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 9/19/2025 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 9/19/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 10/14/2025 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Rough | 10/14/2025 | Approved | KIRK SANDERS |
| HVAC-Rough | 10/14/2025 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 10/14/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 10/21/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Rough | 10/21/2025 | Approved | WILBER ROSALES |
| HVAC-Rough | 10/21/2025 | Partial Approval | WILBER ROSALES |
| Insulation | 10/29/2025 | Approved | WILBER ROSALES |
| Drywall Nailing | 11/4/2025 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 11/10/2025 | Approved | KIRK SANDERS |
| Shower Pan | 11/10/2025 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 1/13/2026 | Corrections Issued | KIRK SANDERS |
| Final | 1/13/2026 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 1/13/2026 | Approved | KIRK SANDERS |
| Green Building Final | 1/13/2026 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 1/13/2026 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 1/13/2026 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 1/13/2026 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 1/13/2026 | Approved | KIRK SANDERS |
| Final | 1/28/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Final | 1/28/2026 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 1/28/2026 | SGSOV Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 2/5/2026 | Approved | RYAN SALAZAR |
| Final | 2/5/2026 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Final | 2/5/2026 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 2/5/2026 | Approved | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 2/9/2026 | Conditional Approval | RYAN SALAZAR |
| Final | 2/11/2026 | OK to Issue CofO | ARAM AVEDISIAN |