1817 N AVENUE 55 90042

Certificate Information: 1817 N AVENUE 55 90042

Application / Permit
25014-10000-00588
Plan Check / Job No.
B25LA05047
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Ground floor addition to an (E) SFD and major remodel to the (E) SFD. (N) slab-on-grade deck at the rear building.
Permit Issued
Issued on 7/11/2025
Issuing Office
Current Status
CofO Issued on 4/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2025 APPLICANT
Assigned to Plan Check Engineer 2/13/2025 HELEN NGUYEN
Corrections Issued 2/19/2025 HELEN NGUYEN
Quality Review Completed 2/20/2025 GARO TELMI
Applicant returned to address corrections 3/25/2025 HELEN NGUYEN
Applicant returned to address corrections 4/25/2025 HELEN NGUYEN
Applicant returned to address corrections 6/6/2025 HELEN NGUYEN
Plan Check Approved 6/27/2025 HELEN NGUYEN
Issued 7/11/2025 APPLICANT
CofO in Progress 4/15/2026 RONNIE MEDINA
Permit Finaled 4/16/2026 DEROLD HAUFF
CofO Issued 4/16/2026 DEROLD HAUFF
Permit Finaled 4/16/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/28/2025 LEE GUILBEAUX
Sewer availability Cleared 2/28/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 2/28/2025 LEE GUILBEAUX
Grading Pre-Inspection Cleared 3/3/2025 LANNY MERRICK
Eng Process Fee Ord 176,300 Cleared 3/4/2025 LEE GUILBEAUX
Low Impact Development (LID) Cleared 3/11/2025 ERNEST TSE
GPI Written Notices Cleared 5/23/2025 HELEN NGUYEN

Contact Information

Contractor Legacy Builders & Remodeling Inc; Lic. No.: 1046784-B       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/15/2025 Conditional Approval JEFFREY MEAD
PLUMBING-Rough 9/3/2025 Partial Approval ALIZAH MAYAGOITIA
Underground Mechanical 9/3/2025 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/5/2025 Partial Approval LILIANA PORTILLO
Special/Order Compliance 9/29/2025 No Access for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/30/2025 Partial Approval DAVID WILLIAMS
ELECTRICAL-Rough 10/27/2025 Not Ready for Inspection RONNIE MEDINA
HVAC-Rough 10/27/2025 Not Ready for Inspection RONNIE MEDINA
PLUMBING-Rough 10/27/2025 Approved RONNIE MEDINA
Deputy Wood Construction 10/28/2025 Conditional Approval GEM DE OCAMPO
BUILDING-Rough-Frame 11/3/2025 Conditional Approval RONNIE MEDINA
ELECTRICAL-Rough 11/3/2025 Approved RONNIE MEDINA
Green Building Rough 11/3/2025 Approved RONNIE MEDINA
HVAC-Rough 11/3/2025 Approved RONNIE MEDINA
Verify Sprinkler Sign Off 11/3/2025 Not Ready for Inspection RONNIE MEDINA
Interior/Exterior Lathing 11/7/2025 Partial Approval ALIZAH MAYAGOITIA
Insulation 11/14/2025 Approved RONNIE MEDINA
Drywall Nailing 11/24/2025 No Access for Inspection RONNIE MEDINA
Drywall Nailing 11/26/2025 Approved RONNIE MEDINA
Interior/Exterior Lathing 12/10/2025 Approved RONNIE MEDINA
Shower Pan 12/10/2025 Corrections Issued RONNIE MEDINA
Shower Pan 12/12/2025 Approved RONNIE MEDINA
Sewer 2/26/2026 Approved LILIANA PORTILLO
ELECTRICAL-Rough 2/27/2026 Approved DAVID WILLIAMS
Underground Mechanical 3/2/2026 Partial Approval RONNIE MEDINA
ELECTRICAL-Final 3/4/2026 Not Ready for Inspection RONNIE MEDINA
Underground Mechanical 3/4/2026 Approved RONNIE MEDINA
Service/Power Release 3/5/2026 Approved RONNIE MEDINA
BUILDING-Rough-Frame 3/24/2026 Partial Approval RONNIE MEDINA
Final 3/24/2026 Corrections Issued RONNIE MEDINA
Footing/Foundation/Slab 3/24/2026 Approved RONNIE MEDINA
Green Building Final 3/24/2026 Approved RONNIE MEDINA
SGSOV-Seismic Gas S/O Valve 3/24/2026 SGSOV Approved RONNIE MEDINA
Smoke Detectors 3/24/2026 Approved RONNIE MEDINA
Verify Sprinkler Sign Off 3/24/2026 Corrections Issued RONNIE MEDINA
BUILDING-Rough-Frame 4/3/2026 Conditional Approval RONNIE MEDINA
Final 4/3/2026 Corrections Issued RONNIE MEDINA
Verify Sprinkler Sign Off 4/3/2026 Corrections Issued RONNIE MEDINA
BUILDING-Rough-Frame 4/15/2026 Approved RONNIE MEDINA
Final 4/15/2026 OK to Issue CofO RONNIE MEDINA
Verify Sprinkler Sign Off 4/15/2026 Approved RONNIE MEDINA