1817 N AVENUE 55 90042
Certificate Information: 1817 N AVENUE 55 90042
- Application / Permit
- 25014-10000-00588
- Plan Check / Job No.
- B25LA05047
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. Ground floor addition to an (E) SFD and major remodel to the (E) SFD. (N) slab-on-grade deck at the rear building.
- Permit Issued
- Issued on 7/11/2025
- Issuing Office
- Current Status
- CofO Issued on 4/16/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2025 | HELEN NGUYEN |
| Corrections Issued | 2/19/2025 | HELEN NGUYEN |
| Quality Review Completed | 2/20/2025 | GARO TELMI |
| Applicant returned to address corrections | 3/25/2025 | HELEN NGUYEN |
| Applicant returned to address corrections | 4/25/2025 | HELEN NGUYEN |
| Applicant returned to address corrections | 6/6/2025 | HELEN NGUYEN |
| Plan Check Approved | 6/27/2025 | HELEN NGUYEN |
| Issued | 7/11/2025 | APPLICANT |
| CofO in Progress | 4/15/2026 | RONNIE MEDINA |
| Permit Finaled | 4/16/2026 | DEROLD HAUFF |
| CofO Issued | 4/16/2026 | DEROLD HAUFF |
| Permit Finaled | 4/16/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/28/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/28/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 2/28/2025 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 3/3/2025 | LANNY MERRICK |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2025 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 3/11/2025 | ERNEST TSE |
| GPI Written Notices | Cleared | 5/23/2025 | HELEN NGUYEN |
Contact Information
| Contractor | Legacy Builders & Remodeling Inc; Lic. No.: 1046784-B | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/15/2025 | Conditional Approval | JEFFREY MEAD |
| PLUMBING-Rough | 9/3/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Underground Mechanical | 9/3/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2025 | Partial Approval | LILIANA PORTILLO |
| Special/Order Compliance | 9/29/2025 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2025 | Partial Approval | DAVID WILLIAMS |
| ELECTRICAL-Rough | 10/27/2025 | Not Ready for Inspection | RONNIE MEDINA |
| HVAC-Rough | 10/27/2025 | Not Ready for Inspection | RONNIE MEDINA |
| PLUMBING-Rough | 10/27/2025 | Approved | RONNIE MEDINA |
| Deputy Wood Construction | 10/28/2025 | Conditional Approval | GEM DE OCAMPO |
| BUILDING-Rough-Frame | 11/3/2025 | Conditional Approval | RONNIE MEDINA |
| ELECTRICAL-Rough | 11/3/2025 | Approved | RONNIE MEDINA |
| Green Building Rough | 11/3/2025 | Approved | RONNIE MEDINA |
| HVAC-Rough | 11/3/2025 | Approved | RONNIE MEDINA |
| Verify Sprinkler Sign Off | 11/3/2025 | Not Ready for Inspection | RONNIE MEDINA |
| Interior/Exterior Lathing | 11/7/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 11/14/2025 | Approved | RONNIE MEDINA |
| Drywall Nailing | 11/24/2025 | No Access for Inspection | RONNIE MEDINA |
| Drywall Nailing | 11/26/2025 | Approved | RONNIE MEDINA |
| Interior/Exterior Lathing | 12/10/2025 | Approved | RONNIE MEDINA |
| Shower Pan | 12/10/2025 | Corrections Issued | RONNIE MEDINA |
| Shower Pan | 12/12/2025 | Approved | RONNIE MEDINA |
| Sewer | 2/26/2026 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 2/27/2026 | Approved | DAVID WILLIAMS |
| Underground Mechanical | 3/2/2026 | Partial Approval | RONNIE MEDINA |
| ELECTRICAL-Final | 3/4/2026 | Not Ready for Inspection | RONNIE MEDINA |
| Underground Mechanical | 3/4/2026 | Approved | RONNIE MEDINA |
| Service/Power Release | 3/5/2026 | Approved | RONNIE MEDINA |
| BUILDING-Rough-Frame | 3/24/2026 | Partial Approval | RONNIE MEDINA |
| Final | 3/24/2026 | Corrections Issued | RONNIE MEDINA |
| Footing/Foundation/Slab | 3/24/2026 | Approved | RONNIE MEDINA |
| Green Building Final | 3/24/2026 | Approved | RONNIE MEDINA |
| SGSOV-Seismic Gas S/O Valve | 3/24/2026 | SGSOV Approved | RONNIE MEDINA |
| Smoke Detectors | 3/24/2026 | Approved | RONNIE MEDINA |
| Verify Sprinkler Sign Off | 3/24/2026 | Corrections Issued | RONNIE MEDINA |
| BUILDING-Rough-Frame | 4/3/2026 | Conditional Approval | RONNIE MEDINA |
| Final | 4/3/2026 | Corrections Issued | RONNIE MEDINA |
| Verify Sprinkler Sign Off | 4/3/2026 | Corrections Issued | RONNIE MEDINA |
| BUILDING-Rough-Frame | 4/15/2026 | Approved | RONNIE MEDINA |
| Final | 4/15/2026 | OK to Issue CofO | RONNIE MEDINA |
| Verify Sprinkler Sign Off | 4/15/2026 | Approved | RONNIE MEDINA |