2248 N GLOVER PL 90031
Certificate Information: 2248 N GLOVER PL 90031
- Application / Permit
- 25014-10000-00549
- Plan Check / Job No.
- B25LA04759
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- One-story ground floor addition to (E) SFD the building will be fire sprinkler with NFPA-13D
- Permit Issued
- Issued on 6/25/2025
- Issuing Office
- Current Status
- CofO Issued on 4/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2025 | GEORGE JOLAKIAN |
| Corrections Issued | 2/20/2025 | GEORGE JOLAKIAN |
| Quality Review Completed | 2/27/2025 | HERNAN ARREOLA |
| Plan Check Approved | 6/18/2025 | GEORGE JOLAKIAN |
| Issued | 6/25/2025 | APPLICANT |
| CofO in Progress | 4/14/2026 | HAMIK HARTOUNIAN |
| Permit Finaled | 4/15/2026 | DEROLD HAUFF |
| CofO Issued | 4/15/2026 | DEROLD HAUFF |
| Permit Finaled | 4/15/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Permit | Cleared | 3/10/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 3/10/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 3/10/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2025 | DAVID LOPEZ |
| ZI | Cleared | 3/17/2025 | GEORGIA SMITH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/14/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 8/25/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 8/25/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Sewer | 8/25/2025 | Approved | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 8/27/2025 | Conditional Approval | ALEX COLIN |
| Excavation/Setback/Form/Re-Bar | 8/27/2025 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 8/27/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 9/8/2025 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 9/8/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| PLUMBING-Rough | 9/10/2025 | Approved | WILLIAM SIERRA |
| Insulation | 9/11/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Special/Order Compliance | 10/2/2025 | Partial Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2025 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2025 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2025 | Partial Approval | BRENDAN MORELLI |
| Deputy Wood Construction | 10/30/2025 | Conditional Approval | ANTHONY RAMOS |
| Special/Order Compliance | 10/30/2025 | No Access for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/13/2025 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 11/13/2025 | Approved | BRENDAN MORELLI |
| Green Building Rough | 11/13/2025 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 11/13/2025 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 11/13/2025 | Partial Approval | BRENDAN MORELLI |
| MERV13>=Rough | 11/13/2025 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 11/13/2025 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 12/4/2025 | Approved | JEFFREY MEAD |
| Insulation | 12/4/2025 | Approved | JEFFREY MEAD |
| Shower Pan | 12/4/2025 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 12/4/2025 | Approved | JEFFREY MEAD |
| Drywall Nailing | 12/8/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 12/23/2025 | Approved | ANTHONY RAMOS |
| Final | 3/19/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 3/19/2026 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Final | 3/19/2026 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 3/19/2026 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 3/19/2026 | Approved | HAMIK HARTOUNIAN |
| Final | 4/9/2026 | OK to Issue CofO | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 4/9/2026 | SGSOV Approved | HAMIK HARTOUNIAN |