1536 W 67TH ST 90047

Certificate Information: 1536 W 67TH ST 90047

Application / Permit
25014-10000-00542
Plan Check / Job No.
B25LA04687
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition (24'-1" x 12'-5) to rear of (E) Single Family Dwelling . The Addition includes (2) bedrooms and (1) bathroom . Interior Remodel to include converting (E) Bedroom to a common Living Room . Work per engineered design .
Permit Issued
Issued on 3/3/2025
Issuing Office
Current Status
CofO Issued on 6/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/6/2025 APPLICANT
Assigned to Plan Check Engineer 2/11/2025 NEHEMIAS RAMOS
Corrections Issued 2/11/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 2/19/2025 NEHEMIAS RAMOS
Plan Check Approved 2/27/2025 GEORGE ALVAREZ
Issued 3/3/2025 APPLICANT
CofO in Progress 6/24/2025 BARRY HACHE
Permit Finaled 6/29/2025 DEROLD HAUFF
CofO Issued 6/29/2025 DEROLD HAUFF
Permit Finaled 6/29/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/21/2025 CHRISTINA BRACO
Sewer availability Cleared 2/21/2025 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 2/26/2025 CHRISTINA BRACO

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/18/2025 Approved BARRY HACHE
Excavation/Setback/Form/Re-Bar 3/25/2025 Approved BARRY HACHE
PLUMBING-Rough 4/3/2025 Corrections Issued JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Approved BARRY HACHE
Sewer 4/8/2025 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 4/10/2025 Partial Approval WAYNE REGESTER
Floor/Roof Diaphrgm/Shear Wall 4/14/2025 Partial Approval BARRY HACHE
Interior/Exterior Lathing 4/17/2025 Approved BARRY HACHE
Masonry Wall/Backfill 4/22/2025 Approved BARRY HACHE
Rough-Elec/Plmb/HVAC 4/22/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 4/25/2025 Approved WAYNE REGESTER
PLUMBING-Rough 4/25/2025 Approved WAYNE REGESTER
Wood Frame 4/25/2025 Approved WAYNE REGESTER
Insulation 4/29/2025 Corrections Issued BARRY HACHE
Shower Pan 4/29/2025 Approved BARRY HACHE
Insulation 5/1/2025 Approved ANTHONY RAMOS
Drywall Nailing 5/5/2025 Approved BARRY HACHE
Interior/Exterior Lathing 5/5/2025 Approved BARRY HACHE
BUILDING-Rough-Frame 5/20/2025 Approved BARRY HACHE
Final 5/20/2025 Corrections Issued BARRY HACHE
Footing/Foundation/Slab 5/20/2025 Approved BARRY HACHE
Green Building Final 5/20/2025 Corrections Issued BARRY HACHE
Green Building Rough 5/20/2025 Approved BARRY HACHE
SGSOV-Seismic Gas S/O Valve 5/20/2025 SGSOV Approved BARRY HACHE
Smoke Detectors 5/20/2025 Approved BARRY HACHE
ELECTRICAL-Final 5/28/2025 Not Ready for Inspection BARRY HACHE
Final 5/28/2025 Corrections Issued BARRY HACHE
Green Building Final 5/28/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Final 6/6/2025 Not Ready for Inspection BARRY HACHE
Final 6/6/2025 Not Ready for Inspection BARRY HACHE
Green Building Final 6/6/2025 Not Ready for Inspection BARRY HACHE
Final 6/23/2025 OK to Issue CofO BARRY HACHE
Green Building Final 6/23/2025 Approved BARRY HACHE
Service/Power Release 6/23/2025 Approved BARRY HACHE