5106 1/2 S CIMARRON ST 90062
Certificate Information: 5106 1/2 S CIMARRON ST 90062
- Application / Permit
- 25014-10000-00538
- Plan Check / Job No.
- B25LA04648
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO A (N) ACCESSORY DWELLING UNIT WITH ADDITION PER LAMC 12.22 A.33(b)(1), (c),(d),(h) AND (k).
- Permit Issued
- Issued on 4/17/2025
- Issuing Office
- Current Status
- CofO Issued on 1/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2025 | GIOVANNY CHAVEZ |
| Corrections Issued | 2/11/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 4/10/2025 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 4/17/2025 | GIOVANNY CHAVEZ |
| Issued | 4/17/2025 | APPLICANT |
| CofO in Progress | 1/21/2026 | SABAS ALONSO |
| Permit Finaled | 1/21/2026 | DEROLD HAUFF |
| CofO Issued | 1/21/2026 | DEROLD HAUFF |
| Permit Finaled | 1/21/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/18/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 2/18/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 2/25/2025 | BIAINA HARITUNIAN |
| Flood clearance | Cleared | 4/8/2025 | SAMSON WONG |
Contact Information
| Contractor | Dwell Homes Llc; Lic. No.: 1030158-B | , |
| Contractor | Dwell Homes Los Angeles; Lic. No.: 1030158-B | , |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 28025 DOROTHY DR STE 202 AGOURA HILLS, CA 91301 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/28/2025 | Approved | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 8/29/2025 | Approved | BARRY HACHE |
| Deputy Drilled-In Anchors | 9/23/2025 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 9/26/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 10/16/2025 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 10/16/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 10/16/2025 | Corrections Issued | SABAS ALONSO |
| Underground Mechanical | 10/16/2025 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 10/20/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 10/20/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 10/20/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 10/20/2025 | Partial Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 10/22/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 10/23/2025 | Approved | SABAS ALONSO |
| Insulation | 10/28/2025 | Approved | SABAS ALONSO |
| Drywall Nailing | 10/31/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 10/31/2025 | Corrections Issued | SABAS ALONSO |
| Underground Mechanical | 10/31/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 11/4/2025 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Final | 1/13/2026 | Not Ready for Inspection | SABAS ALONSO |
| Final | 1/13/2026 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 1/13/2026 | Approved | SABAS ALONSO |
| HVAC-Final | 1/13/2026 | Approved | SABAS ALONSO |
| PLUMBING-Final | 1/13/2026 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 1/13/2026 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 1/13/2026 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 1/15/2026 | Approved | SABAS ALONSO |
| Final | 1/15/2026 | OK to Issue CofO | SABAS ALONSO |
| PLUMBING-Final | 1/15/2026 | Approved | SABAS ALONSO |