5106 1/2 S CIMARRON ST 90062

Certificate Information: 5106 1/2 S CIMARRON ST 90062

Application / Permit
25014-10000-00538
Plan Check / Job No.
B25LA04648
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO A (N) ACCESSORY DWELLING UNIT WITH ADDITION PER LAMC 12.22 A.33(b)(1), (c),(d),(h) AND (k).
Permit Issued
Issued on 4/17/2025
Issuing Office
Current Status
CofO Issued on 1/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/6/2025 APPLICANT
Assigned to Plan Check Engineer 2/11/2025 GIOVANNY CHAVEZ
Corrections Issued 2/11/2025 GIOVANNY CHAVEZ
Applicant returned to address corrections 4/10/2025 ARAMIK SHAHMIRZAIAN
Plan Check Approved 4/17/2025 GIOVANNY CHAVEZ
Issued 4/17/2025 APPLICANT
CofO in Progress 1/21/2026 SABAS ALONSO
Permit Finaled 1/21/2026 DEROLD HAUFF
CofO Issued 1/21/2026 DEROLD HAUFF
Permit Finaled 1/21/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/18/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 2/18/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 2/25/2025 BIAINA HARITUNIAN
Sewer availability Cleared 2/25/2025 BIAINA HARITUNIAN
Flood clearance Cleared 4/8/2025 SAMSON WONG

Contact Information

Contractor Dwell Homes Llc; Lic. No.: 1030158-B       ,
Contractor Dwell Homes Los Angeles; Lic. No.: 1030158-B       ,
Engineer Kazemi,, Milad; Lic. No.: C92143 28025 DOROTHY DR STE 202      AGOURA HILLS, CA 91301

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/28/2025 Approved ALEJANDRO DE ARTOLA
Pre-Inspection 8/29/2025 Approved BARRY HACHE
Deputy Drilled-In Anchors 9/23/2025 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 9/26/2025 Approved SABAS ALONSO
ELECTRICAL-Rough 10/16/2025 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/16/2025 Approved SABAS ALONSO
HVAC-Rough 10/16/2025 Approved SABAS ALONSO
PLUMBING-Rough 10/16/2025 Corrections Issued SABAS ALONSO
Underground Mechanical 10/16/2025 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 10/20/2025 Approved SABAS ALONSO
Green Building Rough 10/20/2025 Approved SABAS ALONSO
PLUMBING-Rough 10/20/2025 Approved SABAS ALONSO
Underground Mechanical 10/20/2025 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 10/22/2025 Approved BARRY HACHE
BUILDING-Rough-Frame 10/23/2025 Approved SABAS ALONSO
Insulation 10/28/2025 Approved SABAS ALONSO
Drywall Nailing 10/31/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 10/31/2025 Corrections Issued SABAS ALONSO
Underground Mechanical 10/31/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 11/4/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 1/13/2026 Not Ready for Inspection SABAS ALONSO
Final 1/13/2026 Corrections Issued SABAS ALONSO
Green Building Final 1/13/2026 Approved SABAS ALONSO
HVAC-Final 1/13/2026 Approved SABAS ALONSO
PLUMBING-Final 1/13/2026 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 1/13/2026 SGSOV Approved SABAS ALONSO
Smoke Detectors 1/13/2026 Approved SABAS ALONSO
ELECTRICAL-Final 1/15/2026 Approved SABAS ALONSO
Final 1/15/2026 OK to Issue CofO SABAS ALONSO
PLUMBING-Final 1/15/2026 Approved SABAS ALONSO