3738 S CHERRYWOOD AVE 90018

Certificate Information: 3738 S CHERRYWOOD AVE 90018

Application / Permit
25014-10000-00530
Plan Check / Job No.
B25LA04542
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and remodel to exsiting single family dwelling
Permit Issued
Issued on 4/1/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/5/2025 APPLICANT
Assigned to Plan Check Engineer 2/20/2025 MATTHEW TORRES
Corrections Issued 2/27/2025 MATTHEW TORRES
Quality Review Completed 3/6/2025 KEN GILL
Building Plans Picked Up 3/7/2025 APPLICANT
Plan Check Approved 3/28/2025 MATTHEW TORRES
No Progress 3/28/2025 MATTHEW TORRES
Plan Check Approved 3/28/2025 MATTHEW TORRES
No Progress 3/28/2025 MATTHEW TORRES
Plan Check Approved 3/28/2025 MATTHEW TORRES
No Progress 3/28/2025 MATTHEW TORRES
Plan Check Approved 3/28/2025 MATTHEW TORRES
Issued 4/1/2025 APPLICANT
CofO in Progress 1/15/2026 LUIS CASTRO
Permit Finaled 1/16/2026 DEROLD HAUFF
CofO Issued 1/16/2026 DEROLD HAUFF
Permit Finaled 1/16/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/11/2025 DAVID VO
Roof/Waste drainage to street Cleared 3/11/2025 DAVID VO
Sewer availability Cleared 3/11/2025 DAVID VO

Contact Information

Contractor Axe Construction Inc; Lic. No.: 1069232-B 6363 WILSHIRE BLVD SUITE 400      LOS ANGELES, CA 90048
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Wood Construction 4/23/2025 Approved LUIS CASTRO
Excavation/Setback/Form/Re-Bar 4/23/2025 Approved LUIS CASTRO
Excavation/Setback/Form/Re-Bar 5/6/2025 Approved LUIS CASTRO
Footing/Foundation/Slab 5/6/2025 Approved LUIS CASTRO
HVAC-Rough 5/6/2025 Not Ready for Inspection LUIS CASTRO
BUILDING-Rough-Frame 5/7/2025 Not Ready for Inspection LUIS CASTRO
Deputy Drilled-In Anchors 5/7/2025 Approved LUIS CASTRO
Green Building Rough 5/7/2025 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 6/3/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 6/4/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 6/9/2025 Partial Approval LUIS CASTRO
Insulation 6/9/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 7/1/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 7/3/2025 Approved LUIS CASTRO
ELECTRICAL-Rough 8/5/2025 Corrections Issued LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 8/5/2025 Partial Approval LUIS CASTRO
HVAC-Rough 8/5/2025 Not Ready for Inspection LUIS CASTRO
Wood Frame 8/5/2025 Not Ready for Inspection LUIS CASTRO
BUILDING-Rough-Frame 8/13/2025 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 8/13/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 8/13/2025 Partial Approval LUIS CASTRO
Shower Pan 8/14/2025 Approved LUIS CASTRO
Wood Frame 8/15/2025 Approved LUIS CASTRO
Insulation 8/18/2025 Not Ready for Inspection LUIS CASTRO
Insulation 8/20/2025 Approved ANTHONY RAMOS
Deputy Drilled-In Anchors 8/22/2025 Conditional Approval JOSH MEISTER
Interior/Exterior Lathing 8/25/2025 Approved RONNIE MEDINA
Footing/Foundation/Slab 8/26/2025 Order to Comply Issued LUIS CASTRO
Drywall Nailing 8/29/2025 Approved LUIS CASTRO
Green Building Rough 8/29/2025 Approved LUIS CASTRO
HVAC-Final 11/25/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 12/1/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Final 12/1/2025 Approved LUIS CASTRO
Footing/Foundation/Slab 12/1/2025 Approved LUIS CASTRO
Gas Test 12/1/2025 Approved LUIS CASTRO
Green Building Final 12/1/2025 Not Ready for Inspection LUIS CASTRO
PLUMBING-Final 12/1/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 12/1/2025 SGSOV Not Ready LUIS CASTRO
Smoke Detectors 12/1/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 12/9/2025 Not Ready for Inspection LUIS CASTRO
Final 12/9/2025 Corrections Issued LUIS CASTRO
Green Building Final 12/9/2025 Not Ready for Inspection LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 12/9/2025 SGSOV Approved LUIS CASTRO
BUILDING-Rough-Frame 12/30/2025 Approved LUIS CASTRO
Final 12/30/2025 Corrections Issued LUIS CASTRO
Green Building Final 12/30/2025 Approved LUIS CASTRO
Final 1/9/2026 Not Ready for Inspection LUIS CASTRO
Final 1/13/2026 Not Ready for Inspection LUIS CASTRO
Final 1/14/2026 OK to Issue CofO LUIS CASTRO