1779 W 37TH PL 90018

Certificate Information: 1779 W 37TH PL 90018

Application / Permit
25014-10000-00522
Plan Check / Job No.
B25LA04463
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REAR ADDITION AND REMODEL OF EXISTING ONE STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 3/17/2025
Issuing Office
Metro
Current Status
CofO Issued on 1/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/5/2025 APPLICANT
Assigned to Plan Check Engineer 2/10/2025 ADAM HEGAZI
Corrections Issued 2/12/2025 ADAM HEGAZI
Building Plans Picked Up 2/21/2025 APPLICANT
Applicant returned to address corrections 3/13/2025 CRISTINA SALAZAR
Plan Check Approved 3/17/2025 AUNG SOE
Issued 3/17/2025 APPLICANT
CofO in Progress 1/6/2026 DEROLD HAUFF
Permit Finaled 1/8/2026 DEROLD HAUFF
CofO Issued 1/8/2026 DEROLD HAUFF
Permit Finaled 1/8/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/13/2025 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 3/13/2025 JUSTIN BICOL

Contact Information

Contractor Rlg Construction; Lic. No.: 1127293-B 5730 LA MIRADA AVE      LOS ANGELES, CA 90038
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/12/2025 Corrections Issued BARRY HACHE
Pre-Inspection 6/12/2025 Approved BARRY HACHE
Deputy Drilled-In Anchors 6/20/2025 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 6/24/2025 Not Ready for Inspection SABAS ALONSO
Deputy Drilled-In Anchors 6/26/2025 No Access for Inspection RONNIE MEDINA
Excavation/Setback/Form/Re-Bar 6/26/2025 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 6/27/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 7/23/2025 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 8/8/2025 Approved SABAS ALONSO
PLUMBING-Rough 8/13/2025 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/22/2025 Not Ready for Inspection BRENDAN MORELLI
HVAC-Rough 8/22/2025 Approved BRENDAN MORELLI
Wood Frame 8/22/2025 Corrections Issued BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 8/28/2025 Corrections Issued JOHN QUINTANILLA
Wood Frame 8/28/2025 Partial Approval JOHN QUINTANILLA
Deputy Wood Construction 8/29/2025 Conditional Approval JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 9/2/2025 Approved SABAS ALONSO
Green Building Rough 9/2/2025 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 9/4/2025 Approved RONNIE MEDINA
BUILDING-Rough-Frame 9/8/2025 Approved SABAS ALONSO
Green Building Rough 9/8/2025 Approved SABAS ALONSO
Insulation 9/8/2025 Approved SABAS ALONSO
Drywall Nailing 9/12/2025 Approved RONNIE MEDINA
Floor/Roof Diaphrgm/Shear Wall 10/27/2025 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 10/28/2025 Approved BRENDAN MORELLI
Insulation 10/28/2025 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 10/30/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 11/4/2025 Approved SABAS ALONSO
ELECTRICAL-Rough 11/4/2025 Approved SABAS ALONSO
PLUMBING-Rough 11/4/2025 Approved SABAS ALONSO
Drywall Nailing 11/6/2025 Approved BARRY HACHE
ELECTRICAL-Final 12/9/2025 Approved LUIS CASTRO
Final 12/9/2025 Corrections Issued LUIS CASTRO
Green Building Final 12/9/2025 Not Ready for Inspection LUIS CASTRO
HVAC-Final 12/9/2025 Corrections Issued LUIS CASTRO
PLUMBING-Final 12/9/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 12/9/2025 SGSOV Approved LUIS CASTRO
Smoke Detectors 12/9/2025 Approved LUIS CASTRO
Final 12/19/2025 Corrections Issued SABAS ALONSO
Green Building Final 12/19/2025 Approved SABAS ALONSO
Final 1/2/2026 OK to Issue CofO SABAS ALONSO