6374 W MACAL PL 90068
Certificate Information: 6374 W MACAL PL 90068
- Application / Permit
- 25014-10000-00517
- Plan Check / Job No.
- B25LA04378
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. New handrail and guardrail for the interior stairway. New decks at fist floor and sublevel. **COMPLY WITH DEPARTMENT ORDER effective date 08/27/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.**
- Permit Issued
- Issued on 8/13/2025
- Issuing Office
- Current Status
- Issued on 8/13/2025
Permit Application Status History
| Submitted | 2/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2025 | HELEN NGUYEN |
| Corrections Issued | 2/18/2025 | HELEN NGUYEN |
| Quality Review Completed | 2/19/2025 | PETER KIM |
| Applicant returned to address corrections | 4/18/2025 | HELEN NGUYEN |
| Applicant returned to address corrections | 4/25/2025 | HELEN NGUYEN |
| Applicant returned to address corrections | 6/6/2025 | HELEN NGUYEN |
| Applicant returned to address corrections | 6/24/2025 | HELEN NGUYEN |
| Plan Check Approved | 8/12/2025 | HELEN NGUYEN |
| Issued | 8/13/2025 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 3/11/2025 | RUBEN VASQUEZ |
| GPI Written Notices | Cleared | 6/6/2025 | HELEN NGUYEN |
| Grading Pre-Inspection | Cleared | 6/6/2025 | HELEN NGUYEN |
| Hold | Cleared | 9/11/2025 | KRISTINE BUENAOBRA |
| Hold | Cleared | 9/24/2025 | KRISTINE BUENAOBRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Steve; Lic. No.: C88484 | 7003 VINING STREET CHINO, CA 91710 |
| Engineer | Sunna,, Nadim; Lic. No.: GE3172 | 27035 MARISCAL LN MISSION VIEJO, CA 92691 |
| Geologist | Rahimikian,, Pedram; Lic. No.: EG2683 | 21414 ARCOS DRIVE WOODLAND HILLS, CA 91364 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/26/2025 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/26/2025 | Corrections Issued | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 10/9/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 10/9/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Piling/Pier/Caisson | 10/9/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Reinforced Concrete Frame | 10/9/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Deck | 10/16/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 10/16/2025 | Approved | CRAIG VAUGHAN |
| Piling/Pier/Caisson | 10/16/2025 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/4/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Pre-Inspection | 11/4/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 11/4/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 11/5/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Deck | 11/21/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Pre-Inspection | 11/21/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 2/5/2026 | Approved | CRAIG VAUGHAN |
| Final | 2/5/2026 | Partial Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 2/5/2026 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 2/5/2026 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 2/5/2026 | Approved | CRAIG VAUGHAN |
| Pre-Inspection | 2/17/2026 | Approved | CRAIG VAUGHAN |
| Wood Frame | 2/17/2026 | Approved | CRAIG VAUGHAN |