15535 W OTSEGO ST 91436
Certificate Information: 15535 W OTSEGO ST 91436
- Application / Permit
- 25014-10000-00506
- Plan Check / Job No.
- B25LA04304
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Convert existing detached garage with addition into new detached ADU per LAMC 12.22 A.33(b)(1)
- Permit Issued
- Issued on 7/2/2025
- Issuing Office
- Current Status
- CofO Issued on 4/16/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2025 | DANIEL SANJUAN |
| Corrections Issued | 2/11/2025 | DANIEL SANJUAN |
| Applicant returned to address corrections | 2/22/2025 | DANIEL SANJUAN |
| Applicant returned to address corrections | 2/27/2025 | ZAW HAN |
| Plan Check Approved | 4/8/2025 | ZAW HAN |
| Issued | 7/2/2025 | APPLICANT |
| CofO in Progress | 3/24/2026 | THOMAS FINNILA |
| Permit Finaled | 4/16/2026 | JOHN JANSON |
| CofO Issued | 4/16/2026 | JOHN JANSON |
| Permit Finaled | 4/16/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/20/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 2/20/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 2/24/2025 | DAVID LOPEZ |
| Construction near power lines | Cleared | 4/1/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 4/1/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Rygaard Construction Inc; Lic. No.: 1125418-B | , |
| Engineer | Southerland,, Richard Charles; Lic. No.: C88965 | 2335 E COLORADO BLVD SUITE 115, # 170 PASADENA, CA 91107 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/9/2025 | Corrections Issued | MORRIS JACKSON |
| Deputy Drilled-In Anchors | 7/25/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 7/29/2025 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 7/29/2025 | Partial Approval | MORRIS JACKSON |
| Rough-Elec/Plmb/HVAC | 9/16/2025 | Partial Inspection | THOMAS FINNILA |
| Sewer | 9/16/2025 | Approved | THOMAS FINNILA |
| Wood Frame | 9/16/2025 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 10/3/2025 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 10/3/2025 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 10/3/2025 | Approved | THOMAS FINNILA |
| Wood Frame | 10/3/2025 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/14/2025 | Partial Approval | MORRIS JACKSON |
| ELECTRICAL-Rough | 10/14/2025 | Approved | MORRIS JACKSON |
| Green Building Rough | 10/14/2025 | Approved | MORRIS JACKSON |
| HVAC-Rough | 10/14/2025 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 10/14/2025 | Approved | MORRIS JACKSON |
| MERV13>=Rough | 10/14/2025 | Approved | MORRIS JACKSON |
| Shower Pan | 10/14/2025 | Approved | MORRIS JACKSON |
| Insulation | 10/21/2025 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2025 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/29/2025 | Approved | MORRIS JACKSON |
| Drywall Nailing | 10/29/2025 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 10/29/2025 | Approved | MORRIS JACKSON |
| Final | 2/2/2026 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 2/2/2026 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 2/24/2026 | Corrections Issued | ROBERT GOLD |
| Green Building Final | 2/24/2026 | Approved | ROBERT GOLD |
| MERV13>=Final | 2/24/2026 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 2/24/2026 | SGSOV Not Ready | ROBERT GOLD |
| Smoke Detectors | 2/24/2026 | Approved | ROBERT GOLD |
| Final | 3/3/2026 | Partial Approval | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 3/3/2026 | SGSOV Approved | THOMAS FINNILA |
| Service/Power Release | 3/5/2026 | Approved | THOMAS FINNILA |
| Final | 3/18/2026 | Corrections Issued | THOMAS FINNILA |