2171 N SAN YSIDRO DR 90210
Certificate Information: 2171 N SAN YSIDRO DR 90210
- Application / Permit
- 25014-10000-00498
- Plan Check / Job No.
- B25LA04262
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Trellis addition and remodel to (E) SFD
- Permit Issued
- Issued on 2/10/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2025 | SHANGQIN XIE |
| Corrections Issued | 2/4/2025 | SHANGQIN XIE |
| Application Withdrawn | 2/4/2025 | APPLICANT |
| Re-Activate Applicaton | 2/4/2025 | APPLICANT |
| Plan Check Approved | 2/10/2025 | SHANGQIN XIE |
| Issued | 2/10/2025 | APPLICANT |
| CofO in Progress | 2/3/2026 | CARLOS MATAMOROS |
| Permit Finaled | 2/5/2026 | RICHARD STEINBACH |
| CofO Issued | 2/5/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/5/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2025 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 2/6/2025 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 2/6/2025 | EDGAR ALCARAZ |
| Grading Pre-Inspection | Cleared | 2/10/2025 | MICHAEL TEMPLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/27/2025 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 5/27/2025 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 7/9/2025 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Rough | 7/9/2025 | Corrections Issued | SEAN HAUPT |
| HVAC-Rough | 7/9/2025 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Rough | 7/9/2025 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 7/14/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 7/14/2025 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 7/14/2025 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 8/1/2025 | Partial Approval | SEAN HAUPT |
| ELECTRICAL-Rough | 8/1/2025 | Partial Approval | SEAN HAUPT |
| Interior/Exterior Lathing | 8/1/2025 | Partial Approval | SEAN HAUPT |
| Insulation | 8/15/2025 | Approved | SEAN HAUPT |
| Special/Order Compliance | 8/15/2025 | Corrections Issued | SEAN HAUPT |
| Drywall Nailing | 8/22/2025 | Approved | SEAN HAUPT |
| Underground Mechanical | 9/2/2025 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 10/2/2025 | Approved | SEAN HAUPT |
| Gas Test | 12/3/2025 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Final | 1/13/2026 | Partial Approval | CARLOS MATAMOROS |
| Gas Test | 1/13/2026 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 1/13/2026 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 2/3/2026 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 2/3/2026 | Approved | CARLOS MATAMOROS |
| Final | 2/3/2026 | OK to Issue CofO | CARLOS MATAMOROS |
| HVAC-Final | 2/3/2026 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 2/3/2026 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 2/3/2026 | Approved | CARLOS MATAMOROS |