2441 N HARWOOD ST 90031
Certificate Information: 2441 N HARWOOD ST 90031
- Application / Permit
- 25014-10000-00469
- Plan Check / Job No.
- B25LA04068
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN***PROPOSED MAJOR REMODEL AND ADDITION WITH ATACHED GARAGE TO SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 8/27/2025
- Issuing Office
- Current Status
- Issued on 8/27/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2025 | SINA KHOSRAVI |
| Corrections Issued | 2/11/2025 | SINA KHOSRAVI |
| Quality Review Completed | 2/14/2025 | GARO TELMI |
| Applicant returned to address corrections | 7/7/2025 | SINA KHOSRAVI |
| Applicant returned to address corrections | 7/24/2025 | SINA KHOSRAVI |
| Plan Check Approved | 8/14/2025 | SINA KHOSRAVI |
| Plan Check Approved | 8/26/2025 | INTERNET PERMIT |
| Issued | 8/27/2025 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/11/2025 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2025 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 2/18/2025 | ERIK BEASLEY |
| ZI | Cleared | 6/17/2025 | DORIAN AGUILAR |
Contact Information
| Architect | Abdelsayed,, Marc A; Lic. No.: C38176 | 280 VIA LINDA VISTA REDONDO BEACH, CA 90277 |
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/18/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 10/3/2025 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2025 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2026 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 1/21/2026 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/9/2026 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 2/11/2026 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/11/2026 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 2/11/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Insulation | 2/13/2026 | No Access for Inspection | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 2/18/2026 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 2/18/2026 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 2/18/2026 | Partial Approval | HAMIK HARTOUNIAN |
| Shower Pan | 2/18/2026 | Approved | HAMIK HARTOUNIAN |
| Insulation | 2/19/2026 | Approved | HAMIK HARTOUNIAN |
| Special/Order Compliance | 2/19/2026 | Partial Inspection | OSVALDO PARAMO |
| Drywall Nailing | 2/24/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| Interior/Exterior Lathing | 2/24/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| Drywall Nailing | 2/26/2026 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 2/26/2026 | Approved | HAMIK HARTOUNIAN |
| Sewer | 6/9/2026 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 6/9/2026 | Partial Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 6/12/2026 | Partial Approval | JEFFREY MEAD |
| Underground Mechanical | 6/16/2026 | Approved | HAMIK HARTOUNIAN |