1469 S CARDIFF AVE 90035
Certificate Information: 1469 S CARDIFF AVE 90035
- Application / Permit
- 25014-10000-00455
- Plan Check / Job No.
- B25LA03983
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan - Convert (E) 1-story detached garage and recreation room and addition to ADU per LAMC 12.22A.33 (c), (d), (h), (k) R3 occupancy NFPA 13D sprinklered throughout
- Permit Issued
- Issued on 4/7/2025
- Issuing Office
- Current Status
- CofO Issued on 2/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2025 | KELVIN CHUONG |
| Corrections Issued | 2/8/2025 | KELVIN CHUONG |
| Plan Check Approved | 4/2/2025 | FERNANDO FLORES |
| Issued | 4/7/2025 | APPLICANT |
| CofO in Progress | 2/6/2026 | ASHLEY THOMPSON |
| Permit Finaled | 2/7/2026 | RICHARD STEINBACH |
| CofO Issued | 2/7/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/7/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/19/2025 | VASIL MIHALEV |
| Address approval | Cleared | 2/22/2025 | KIMBERLY HERNANDEZ |
| Sewer availability | Cleared | 2/22/2025 | KIMBERLY HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2025 | KIMBERLY HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 3/3/2025 | KIMBERLY HERNANDEZ |
| Construction near power lines | Cleared | 3/24/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/5/2025 | Corrections Issued | ASHLEY THOMPSON |
| METHANE-Barrier | 8/5/2025 | Approved | ASHLEY THOMPSON |
| METHANE-Subgrade | 8/5/2025 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 8/5/2025 | Partial Approval | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 9/4/2025 | Approved | EVAN COOPER |
| PLUMBING-Rough | 10/24/2025 | Approved | EVAN COOPER |
| Deputy Wood Construction | 10/28/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 10/28/2025 | Conditional Approval | MEL KHACHATOURIAN |
| HVAC-Rough | 10/28/2025 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 10/29/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2025 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Rough | 10/29/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| METHANE-Rough | 10/29/2025 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 11/5/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2025 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 11/5/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Deputy Wood Construction | 11/12/2025 | Conditional Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 11/14/2025 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 11/14/2025 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 11/14/2025 | Partial Approval | ASHLEY THOMPSON |
| Insulation | 11/18/2025 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 11/21/2025 | Approved | EVAN COOPER |
| Final | 11/21/2025 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Final | 1/29/2026 | Corrections Issued | ASHLEY THOMPSON |
| Final | 1/29/2026 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 1/29/2026 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 1/29/2026 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 1/29/2026 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 1/29/2026 | SGSOV Not Ready | ASHLEY THOMPSON |
| Smoke Detectors | 1/29/2026 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 2/3/2026 | Approved | ASHLEY THOMPSON |
| Final | 2/3/2026 | OK to Issue CofO | ASHLEY THOMPSON |
| HVAC-Final | 2/3/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 2/3/2026 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 2/3/2026 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 2/3/2026 | Approved | ASHLEY THOMPSON |