8041 S DUNFIELD AVE 90045

Certificate Information: 8041 S DUNFIELD AVE 90045

Application / Permit
25014-10000-00451
Plan Check / Job No.
B25LA03957
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Addition and remodel to existing one story single family dwelling.
Permit Issued
Issued on 4/7/2025
Issuing Office
Current Status
CofO Issued on 1/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2025 APPLICANT
Assigned to Plan Check Engineer 2/6/2025 SAMUEL GONZALEZ
Corrections Issued 2/7/2025 SAMUEL GONZALEZ
Applicant returned to address corrections 3/10/2025 SAMUEL GONZALEZ
Plan Check Approved 3/13/2025 DANIEL YIP
Issued 4/7/2025 APPLICANT
CofO in Progress 1/9/2026 ANTHONY EGSON
Permit Finaled 1/17/2026 RICHARD STEINBACH
CofO Issued 1/17/2026 RICHARD STEINBACH
Permit Finaled 1/17/2026 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/9/2025 KATHLEEN LEE
Roof/Waste drainage to street Cleared 3/9/2025 KATHLEEN LEE
Sewer availability Cleared 3/9/2025 KATHLEEN LEE

Contact Information

Contractor Nittay Inc; Lic. No.: 1033506-B       ,
Contractor P M A Renovations; Lic. No.: 1033506-B       ,
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/20/2025 Approved RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 5/27/2025 Not Ready for Inspection RUBEN RIVAS
Underground Mechanical 5/27/2025 Partial Approval RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 5/30/2025 Approved RUBEN RIVAS
Deputy Steel/Welding 6/2/2025 Partial Approval RUBEN RIVAS
BUILDING-Rough-Frame 7/14/2025 Not Ready for Inspection RUBEN RIVAS
ELECTRICAL-Rough 7/14/2025 Approved RUBEN RIVAS
Green Building Rough 7/14/2025 Not Ready for Inspection RUBEN RIVAS
HVAC-Rough 7/14/2025 Approved RUBEN RIVAS
BUILDING-Rough-Frame 7/17/2025 Approved RUBEN RIVAS
Green Building Rough 7/17/2025 Approved RUBEN RIVAS
Interior/Exterior Lathing 7/17/2025 Approved RUBEN RIVAS
PLUMBING-Rough 7/17/2025 Approved RUBEN RIVAS
Insulation 7/28/2025 Approved RUBEN RIVAS
Interior/Exterior Lathing 7/28/2025 Approved RUBEN RIVAS
Drywall Nailing 8/4/2025 Approved MICHAEL ALLEN
Verify Sprinkler Sign Off 8/4/2025 Partial Approval MICHAEL ALLEN
ELECTRICAL-Final 12/8/2025 Corrections Issued ANTHONY EGSON
Green Building Final 12/8/2025 Approved ANTHONY EGSON
HVAC-Final 12/8/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Final 12/8/2025 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 12/8/2025 SGSOV Approved ANTHONY EGSON
Smoke Detectors 12/8/2025 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 1/9/2026 Approved ANTHONY EGSON
Final 1/9/2026 OK to Issue CofO ANTHONY EGSON
HVAC-Final 1/9/2026 Approved ANTHONY EGSON
Smoke Detectors 1/9/2026 Approved ANTHONY EGSON